Donegal County Council · 2351908
Raneany West, Laghy, Donegal PO
Approved in Mar 2024. Building started in 2024.
- 12 Dec 2023Received
- 1 Feb 2024Conditional
- 6 Mar 2024Final approval
- 23 Apr 2024Building started
- Status
- Building startedi
- Decision
- Conditional · 1 Feb 2024
- Council
- Donegal County Council
- Type
- PERMISSION
- Units
- 1
- Site
- 4,068 m²
What’s proposed
CONSTRUCTION OF A DWELLING HOUSE WITH SEWAGE TREATMENT SYSTEM AND ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS
Planning details
- Reference
- 2351908
- Local authority
- Donegal County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 12 Dec 2023
- Decision due
- 14 Feb 2024 · decided 1 Feb 2024
- Decision
- Conditional on 1 Feb 2024
- Site area
- 4,068 m² from the mapped boundary, not the council's figure
Nearby 1 · 500 m · 12 months
Distance
Time
Homes nearby
Building started
- 23 Apr 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0113053DL
Not held yet for Donegal County Council: zoning.
Protections nearby 250 m
- NIAH-recorded building · 1
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2351908 is a planning application to Donegal County Council for construction of a dwelling house with sewage treatment system and all other associated, received on 12 Dec 2023; permission was granted with conditions on 1 Feb 2024.