Donegal County Council · 2450255
Tullyillan, Burtonport, Letterkenny PO
Approved in Sept 2025. Building started in 2026.
- 4 Dec 2024Received
- 14 Aug 2025Conditional
- 17 Sept 2025Final approval
- 28 Jul 2026Building started
- Status
- Building startedi
- Decision
- Conditional · 14 Aug 2025
- Council
- Donegal County Council
- Type
- PERMISSION
- Units
- 1
- Site
- 2,478 m²
What’s proposed
CONSTRUCTION OF A NEW DWELLING HOUSE AND INSTALLATION OF A WASTEWATER TREATMENT SYSTEM WITH ALL ASSOCIATED DRAINAGE AND SITE WORKS
Planning details
- Reference
- 2450255
- Local authority
- Donegal County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 4 Dec 2024
- Observations close
- 17 Jan 2025 (closed 642 days ago)
- Decision due
- 25 Aug 2025 · decided 14 Aug 2025
- Decision
- Conditional on 14 Aug 2025
- Site area
- 2,478 m² from the mapped boundary, not the council's figure
Nearby 10 · 500 m · 5 years
- GrantedROSHIN NORTH , BURTONPORT , LETTERKENNY PO
- Awaiting decisionROSHIN NORTH , BURTONPORT , LETTERKENNY PO
- WithdrawnROSHIN NORTH , BURTONPORT , LETTERKENNY PO
- WithdrawnROSHIN NORTH , BURTONPORT , LETTERKENNY
- GrantedTULLYILLAN , BURTONPORT , LETTERKENNY PO
- CommencedTULLYILLAN , BURTONPORT , LETTERKENNY PO
- WithdrawnTULLYILLAN , BURTONPORT , LETTERKENNY PO
- CommencedTULLYILLAN , BURTONPORT , LETTERKENNY
Show all 10
Homes nearby
Building started
- 28 Jul 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0145281DL
Not held yet for Donegal County Council: zoning.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2450255 is a planning application to Donegal County Council for construction of a new dwelling house and installation of a wastewater treatment system, received on 4 Dec 2024; permission was granted with conditions on 14 Aug 2025.