What’s proposed

A TEN-YEAR PERMISSION FOR A GRID SERVICES FACILITY COMPRISING OF (1) AN ENCLOSED BATTERY ENERGY STORAGE SYSTEM COMPOUND CONTAINING BATTERY ENERGY STORAGE CONTAINERS, ELECTRICAL INVERTERS, TRANSFORMERS AND POWER CONTROL CENTRES, (2) AN ENCLOSED SYNCHRONOUS CONDENSER COMPOUND CONTAINING A HORIZONTAL SYNCHRONOUS GENERATOR HOUSED WITHIN A SYNCHRONOUS CONDENSER BUILDING AND ANCILLARY INFRASTRUCTURE INCLUDING A FLYWHEEL…

Show all

TRANSFORMER, CIRCUIT BREAKER AND COOLING EQUIPMENT, (3) UNDERGROUND ELECTRICAL AND COMMUNICATIONS CABLING, (4) SITE ENTRANCE FROM THE L7965-1 LOCAL ROAD, (5) ON-SITE ACCESS TRACK, (6) SECURITY FENCING AND SECURITY GATES, (7) POLE-MOUNTED SECURITY CAMERAS, (8) ALL ASSOCIATED AND ANCILLARY SITE DEVELOPMENT, LANDSCAPING AND REINSTATEMENT WORKS. THE OPERATIONAL LIFETIME OF THE PROPOSED DEVELOPMENT IS 35 YEARS. THIS PLANNING APPLICATION IS ACCOMPANIED BY AN APPROPRIATE ASSESSMENT SCREENING REPORT

  1. 22 Feb 2024Received
  2. 25 Nov 2024Refused

An email when the appeal is decided, and if building then starts.

Planning details

Status
Under appeal
Decision
Refused · 25 Nov 2024
Reference
2460197
Received
22 Feb 2024
Further information
Requested 11 Apr 2024 · received 5 Oct 2024
Site
5.87 ha

Every application, appeal and deadline within 500 m

Get the full report

Explore this area on the map →

Homes nearby

Appeal

Appeal ABP-321512-24 (status unknown), not yet matched.

Not held yet for Donegal County Council: zoning.

Protections nearby 250 m

  • Recorded monument · 7
    Enclosure; Ringfort - rath
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2460197 is a planning application to Donegal County Council for a ten-year permission for a grid services facility comprising of (1) an enclosed battery, received on 22 Feb 2024; permission was refused on 25 Nov 2024.