PlanningRegister.ie
Donegal County Council · 2560413

Gortaway, Ramelton, Letterkenny PO

Approved in Jun 2025. Building started in 2025.

  1. 21 Mar 2025Received
  2. 1 May 2025Conditional
  3. 4 Jun 2025Final approval
  4. 21 Jul 2025Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Building startedi
Decision
Conditional · 1 May 2025
Council
Donegal County Council
Type
PERMISSION
Units
1
Site
3,104 m²

Live near Gortaway?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

DEMOLITION OF EXISTING DWELLING HOUSE DAMAGED DUE TO DEFECTIVE MASONRY CONCRETE BLOCKS (MICA) AND ERECTION OF A REPLACEMENT DWELLING HOUSE OF AN ALTERNATIVE DESIGN WITH CONNECTION TO ALL EXISTING SERVICES ON SITE INCLUDING ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS

Planning details

Reference
2560413
Local authority
Donegal County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
21 Mar 2025
Observations close
25 Apr 2025 (closed 538 days ago)
Decision due
15 May 2025 · decided 1 May 2025
Decision
Conditional on 1 May 2025
Site area
3,104 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 5 · 500 m · 5 years

Explore this area on the map →

Building started

  • 21 Jul 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0131224DL

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

  • NIAH-recorded building · 1
    farmyard complex

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

2560413 is a planning application to Donegal County Council for demolition of existing dwelling house damaged due to defective masonry concrete blocks, received on 21 Mar 2025; permission was granted with conditions on 1 May 2025.