What’s proposed
VARIATION OF CONDITION NO. 4 OF PERMISSION GRANTED FOR CRILLY WIND FARM (PLANNING REF. NO. 13/51404 AND AN COIMISIÚN PLEANÁLA REF. ABP PL 05E.245588 REFERS) WHICH RELATES TO THE DURATION OF THE CONSTRUCTION WORKS TO FACILITATE THE PERMITTED DEVELOPMENT. IT IS PROPOSED TO VARY CONDITION NO. 4 TO EXTEND THE DURATION OF THE CONSTRUCTION WORKS BY 5 YEARS TO FACILITATE THE CONSTRUCTION OF THE PREVIOUSLY PERMITTED DEVELOPMENT COMPRISING 4 NO. WIND TURBINES WITH A MAXIMUM BLADE DIAMETER OF 93M AND A MAXIMUM BLADE TIP HEIGHT OF 126.5M, ALL ANCILLARY DEVELOPMENTS AND ASSOCIATED SITE DEVELOPMENT WORKS. THE PERMITTED DEVELOPMENT INCLUDES ACCESS OFF SEEGRONAN ROAD, KILLETER, CASTLEDERG, CO. TYRONE AND NO ALTERATION IS PROPOSED TO THE NATURE, SCALE OR DESIGN OF THE PERMITTED DEVELOPMENT. THIS DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
Planning details
- Reference
- 2661665
- Local authority
- Donegal County Council
- Status
- Open for observation · register status “NEW APPLICATION”
- Received
- 8 Sept 2026
- Observations close
- 13 Oct 2026 (7 days left)
- Decision due
- 2 Nov 2026
- Decision
- Not decided
- Proposed development
- VARIATION OF CONDITION NO. 4 OF PERMISSION GRANTED FOR CRILLY WIND FARM (PLANNING REF. NO. 13/51404 AND AN COIMISIÚN PLEANÁLA REF. ABP PL 05E.245588 REFERS) WHICH RELATES TO THE DURATION OF THE CONSTRUCTION WORKS TO FACILITATE THE PERMITTED DEVELOPMENT. IT IS PROPOSED TO VARY CONDITION NO. 4 TO EXTEND THE DURATION OF THE CONSTRUCTION WORKS BY 5 YEARS TO FACILITATE THE CONSTRUCTION OF THE PREVIOUSLY PERMITTED DEVELOPMENT COMPRISING 4 NO. WIND TURBINES WITH A MAXIMUM BLADE DIAMETER OF 93M AND A MAXIMUM BLADE TIP HEIGHT OF 126.5M, ALL ANCILLARY DEVELOPMENTS AND ASSOCIATED SITE DEVELOPMENT WORKS. THE PERMITTED DEVELOPMENT INCLUDES ACCESS OFF SEEGRONAN ROAD, KILLETER, CASTLEDERG, CO. TYRONE AND NO ALTERATION IS PROPOSED TO THE NATURE, SCALE OR DESIGN OF THE PERMITTED DEVELOPMENT. THIS DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)As published by the register.
- Site area
- 24.46 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby none · 500 m · 5 years
No other application within 500 m in the last 5 years.
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
Nothing else protected nearby.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
2661665 is a planning application to Donegal County Council for variation of condition no. 4 of permission granted for crilly wind farm (planning ref., received on 8 Sept 2026; observations close on 13 Oct 2026 (7 days left).