PlanningRegister.ie
Galway County Council · 212016

Gort an Chalaidh

Approved in Apr 2022. Building started in 2023.

  1. 28 Oct 2021Received
  2. 2 Mar 2022Conditional
  3. 11 Apr 2022Final approval
  4. 22 Mar 2023Building started

Planning details

Status
Building startedi
Decision
Conditional · 2 Mar 2022
Reference
212016
Received
28 Oct 2021
Further information
Requested 21 Dec 2021 · received 3 Feb 2022
Units
1
Site
3,260 m²

What’s proposed

For a development consisting of alterations to the existing cottage roof, construction of a new two storey & single storey extension to the rear of the existing cottage, internal alterations to the existing cottage, new WWTS and all ancillary site works. A Natura Impact Statement will be submitted to the planning authority with the application. Gross floor space of the proposed works: 222.15 sqm

2 other applications within 500 m in the last year · 1 open for comments

Open the report

Nearby 2 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 22 Mar 2023 · Builder told the council work was starting (opted out of the finish sign-off) CN0098823GC

Protections nearby 250 m

  • Recorded monument · 1
    R127244
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

212016 is a planning application to Galway County Council for for a development consisting of alterations to the existing cottage roof, construction, received on 28 Oct 2021; permission was granted with conditions on 2 Mar 2022.