Lacklea
Approved in Jan 2022.
- 9 Nov 2021Received
- 12 Jan 2022Conditional
- 21 Feb 2022Final approval
- 20 Feb 2027Approval runs out
- Status
- Approved
- Decision
- Conditional · 12 Jan 2022
- Council
- Galway County Council
- Type
- RETENTION
- Units
- 1
- Site
- 9,875 m²
What’s proposed
of the existing dwelling house and garage on a site with revised boundaries. Gross floor space of works to be retained 382.20 sqm
Planning details
- Reference
- 212082
- Local authority
- Galway County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 9 Nov 2021
- Decision due
- 12 Jan 2022 · decided 12 Jan 2022
- Decision
- Conditional on 12 Jan 2022
- Site area
- 9,875 m² from the mapped boundary, not the council's figure
Nearby 3 · 500 m · 12 months
- Awaiting decisionNa Foraí Maola Thoir , Barna , Co Galway
- GrantedRinn na Mara , Seapoint Barna , Co Galway
- GrantedÁit An Ghlugair , 6 Creagan Barna , Co. Galway
Homes nearby
Zoning
Open space with active recreational amenities — pitches, courts, play areas.
Protected high-amenity landscape. Development is resisted to preserve the character of the area.
Tied to the efficient operation and development of the airport under its own plan — which also means aircraft noise contours apply.
An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
Protections nearby 250 m
- Recorded monument · 1
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
212082 is a planning application to Galway County Council for of the existing dwelling house and garage on a site with revised boundaries. Gross floor, received on 9 Nov 2021; permission was granted with conditions on 12 Jan 2022.