Cloonascragh, Tuam, Co. Galway
Approved in Nov 2023. No sign of building yet.
Start notices are matched from the national building control register; a start on site can be missed.
- 17 Nov 2022Received
- 9 Oct 2023Conditional
- 20 Nov 2023Final approval
- 19 Nov 2033Approval runs out
Planning details
- Status
- Approved
- Decision
- Conditional · 9 Oct 2023
- Reference
- 221175
- Received
- 17 Nov 2022
- Further information
- Requested 20 Jan 2023 · received 12 Sept 2023
- Units
- 1
- Site
- 4.37 ha
What’s proposed
For the development consisting of a wind energy development comprising of one electricity generating wind turbine, with an overall blade tip height of up to 168m, construction of c. 150m of permanent access track, 110m of temporary access track, road widening works along the existing local access road from the R327 to the proposed site access track, a crane hardstand, a 20kV substation, site electrical & fibre optic…
Show all
cabling & ancillary site works. The maximum output capacity of the wind farm will be c.4.8MW. This application is seeking a 10 year permission & a 35 year operational life from the date of commissioning of the wind farm. The planning application is accompanied by Natura Impact Statement (NIS)
3 other applications within 500 m in five years
Open the reportNearby 3 · 500 m · 5 years
Homes nearby
Protections nearby 250 m
- Recorded monument · 2
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
221175 is a planning application to Galway County Council for for the development consisting of a wind energy development comprising of one, received on 17 Nov 2022; permission was granted with conditions on 9 Oct 2023.