Galway County Council · 2461272
Lenamore, Colemanstown, Ballinasloe
Approved in Apr 2025. Building started in 2025.
- 27 Sept 2024Received
- 4 Mar 2025Conditional
- 14 Apr 2025Final approval
- 21 Jul 2025Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
- Status
- Building startedi
- Decision
- Conditional · 4 Mar 2025
- Council
- Galway County Council
- Type
- PERMISSION
- Units
- 1
- Site
- 2,008 m²
What’s proposed
to construct a new dwelling house, wastewater treatment system, domestic garage, and all associated site works. Gross floor space of proposed work: 115.00 sqm (house) & 60.00 sqm (garage)
Planning details
- Reference
- 2461272
- Local authority
- Galway County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 27 Sept 2024
- Observations close
- 1 Nov 2024 (closed 707 days ago)
- Decision due
- 5 Mar 2025 · decided 4 Mar 2025
- Decision
- Conditional on 4 Mar 2025
- Proposed development
- to construct a new dwelling house, wastewater treatment system, domestic garage, and all associated site works. Gross floor space of proposed work: 115.00 sqm (house) & 60.00 sqm (garage)As published by the register.
- Site area
- 2,008 m² from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 1 · 500 m · 5 years
Homes nearby
Building started
- 21 Jul 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0130973GC
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
Nothing else protected nearby.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
2461272 is a planning application to Galway County Council for to construct a new dwelling house, wastewater treatment system, domestic garage, and all, received on 27 Sept 2024; permission was granted with conditions on 4 Mar 2025.