Galway County Council · 2561117
Brockagh, Castlegar, Co. Galway
Approved in Nov 2025. Building started in 2026.
- 14 Aug 2025Received
- 7 Oct 2025Conditional
- 18 Nov 2025Final approval
- 27 Apr 2026Building started
- Status
- Building startedi
- Decision
- Conditional · 7 Oct 2025
- Council
- Galway County Council
- Type
- PERMISSION
- Units
- 1
- Site
- 2,980 m²
What’s proposed
to construct a serviced dwelling house, with a connection to a new wastewater treatment system, and domestic garage
Planning details
- Reference
- 2561117
- Local authority
- Galway County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 14 Aug 2025
- Decision due
- 8 Oct 2025 · decided 7 Oct 2025
- Decision
- Conditional on 7 Oct 2025
- Site area
- 2,980 m² from the mapped boundary, not the council's figure
Nearby 3 · 500 m · 5 years
Distance
Time
Homes nearby
Building started
- 27 Apr 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0140882GC
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2561117 is a planning application to Galway County Council for to construct a serviced dwelling house, with a connection to a new wastewater treatment, received on 14 Aug 2025; permission was granted with conditions on 7 Oct 2025.