Galway County Council · 2561265
Rushestown, Newbridge Ballinasloe, Co. Galway
Approved in Dec 2025. Building started in 2026.
- 5 Sept 2025Received
- 28 Oct 2025Conditional
- 9 Dec 2025Final approval
- 6 Apr 2026Building started
- Status
- Building startedi
- Decision
- Conditional · 28 Oct 2025
- Council
- Galway County Council
- Type
- PERMISSION
- Site
- 4,119 m²
What’s proposed
to construct a new dwelling house with wastewater treatment plant, polishing filter, domestic garage and all associated site works
Planning details
- Reference
- 2561265
- Local authority
- Galway County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 5 Sept 2025
- Observations close
- 10 Oct 2025 (closed 377 days ago)
- Decision due
- 30 Oct 2025 · decided 28 Oct 2025
- Decision
- Conditional on 28 Oct 2025
- Site area
- 4,119 m² from the mapped boundary, not the council's figure
Nearby 4 · 500 m · 5 years
Building started
- 6 Apr 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0140308GC
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2561265 is a planning application to Galway County Council for to construct a new dwelling house with wastewater treatment plant, polishing filter, received on 5 Sept 2025; permission was granted with conditions on 28 Oct 2025.