Ballinvosherig West, Kielduff, Tralee
Approved in Feb 2022. Building started.
- 21 Dec 2021Received
- 23 Feb 2022Conditional
- 29 Mar 2022Final approval
- 10 Feb 2025Building started
- 28 Mar 2027Approval runs out
Planning details
- Status
- Building started
- Decision
- Conditional · 23 Feb 2022
- Reference
- 211479
- Type
- RETENTION
- Received
- 21 Dec 2021
- Units
- 1
- Site
- 3,692 m²
What’s proposed
(A) RETAIN ON SITE STRUCTURES AND EXISTING ONSITE TREATMENT SYSTEM WITHIN REVISED SITE BOUNDARIES (B) PLANNING PERMISSION TO REVISE DWELLING HOUSE DESIGN AS GRANTED UNDER PLANNING REFERENCE 14/177 WHEREBY THE ORIGINAL EXISTING DWELLING HOUSE IS TO BE DEMOLISHED AND REPLACED WITH A PROPOSED STOREY AND A HALF STYLE STURCUTRE ONTO THE SIDE OF THE INSITU EXTENSION AS WAS APPROVED UNDER PLANNING REFERENCE 14/177; (C) PLANNING PERMISSION TO CONSTRUCT INTEGRATED OPEN SIDED STORAGE
2 other applications within 500 m in the last year · 1 open for comments
Open the reportNearby 2 · 500 m · 12 months
Homes nearby
Building started
- 10 Feb 2025 · Builder told the council work was starting (opted out of the finish sign-off) CN0125140KY
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
211479 is a planning application to Kerry County Council for (a) retain on site structures and existing onsite treatment system within revised site, received on 21 Dec 2021; permission was granted with conditions on 23 Feb 2022.