Coolard Coolkeragh and Glouria, Listowel, Co Kerry
Approved in Mar 2023. Building started in 2025, signed off as finished in Jul 2026.
- 21 Dec 2022Received
- 23 Feb 2023Conditional
- 29 Mar 2023Final approval
- 31 Oct 2025Building started
- 24 Jul 2026Signed off
Planning details
- Status
- Building started
- Decision
- Conditional · 23 Feb 2023
- Reference
- 221340
- Received
- 21 Dec 2022
- Site
- 2.55 ha
What’s proposed
MODIFY THE APPROVED GRID CONNECTION FOR THE BALLYDONOHOE SOLAR FARM AS PERMITTED UNDER KERRY COUNTY COUNCIL REFERENCE 21457/AN BORD PLEANÁLA REFERENCE 312288. THE MODIFCATIONS COMPRISE OF (1) THE PROVISION OF A MV CONTROL BUILDING WITHIN THE SOLAR FARM, (2) THE LAYING OF C. 1,747 METRES OF 33KV UNDERGROUND CABLING WITH THE SOLAR FARM SITE, L-1008 AND ADJACENT PUBLIC ROAD TO BE INSTALLED IN AN EXCAVATED TRENCH…
Show all
INCLUDING UNDERGROUND DUCTING, JOINT BAYS, COMMUNICATION CHAMBERS AND ALL ASSOCIATED SITE DEVELOPMENT AND REINSTATEMENT WORKS, AND (3) MINOR RELOCATION OF POLE SETS AND ASSOCIATED 33KV OVER-HEAD WIRES WITHIN A C. 216 METRES SECTION OF OVERHEAD LINES ON PRIVATE LANDS
Every application, appeal and deadline within 500 m
Open the reportNearby none · 500 m · 5 years
No other application within 500 m in the last 5 years.
Homes nearby
Building started
- 31 Oct 2025 · Builder told the council work was starting (seven-day notice) SN0013281KY
Protections nearby 250 m
- Recorded monument · 8
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
221340 is a planning application to Kerry County Council for modify the approved grid connection for the ballydonohoe solar farm as permitted under, received on 21 Dec 2022; permission was granted with conditions on 23 Feb 2023.