Approved in Oct 2022. Building started in 2024.

  1. 3 Mar 2022Received
  2. 10 Oct 2022Conditional
  3. 10 Oct 2024Building started

Planning details

Status
Building startedi
Decision
Conditional · 10 Oct 2022
Reference
22228
Received
3 Mar 2022
Further information
Requested 26 Apr 2022 · received 13 Sept 2022
Site
2.67 ha

What’s proposed

CONSTRUCT A BIOGAS PRODUCTION PLANT INCORPORATING: TWO DIGESTION TANKS, A PRE-MIX TANK AND DIGESTATE TANK, A SUBSTRATE STORAGE AREA AND SLURRY STORAGE TANK WITH ASSOCIATED PUMPS, TO CONSTRUCT A BUILDING CONTAINING CHP UNIT AND CONTROLS FOR DIGESTION FACILITY AND MACHINERY STORAGE, A CONCRETE UNDERGROUND COVERED SOILED WATER TANK WITH WHEEL WASH, WEIGHBRIDGE, AND BIOGAS FARE UNIT, TO CONSTRUCT A WATER ATTENUATION TANK…

Show all

FOR STORM/RAIN WATER ON SITE, COMPLETE WITH CLASS 1 OIL INTERCEPTOR/SEPARATOR, SILT TRAPS, TREE LINED BOUNDARY FENCE ON EARTHEN BANK AND ALL SSSOCIATED SITE WORKS

3 other applications within 500 m in the last year

Open the report

Nearby 3 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Appeal

Appeal 315040-22 (status unknown), not yet matched.

Building started

  • 10 Oct 2024 · Builder told the council small works were starting CN0121227KY

Protections nearby 250 m

  • Recorded monument · 6
    Ringfort - rath; Cist
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

22228 is a planning application to Kerry County Council for construct a biogas production plant incorporating: two digestion tanks, a pre-mix tank, received on 3 Mar 2022; permission was granted with conditions on 10 Oct 2022.