Approved in Aug 2023. Building started.

  1. 28 Feb 2023Received
  2. 11 Aug 2023Conditional
  3. 14 Sept 2023Final approval
  4. 9 May 2024Building started
  5. 13 Sept 2028Approval runs out

Planning details

Status
Building started
Decision
Conditional · 11 Aug 2023
Reference
23219
Type
RETENTION
Received
28 Feb 2023
Further information
Requested 21 Apr 2023 · received 7 Jul 2023
Units
1
Site
2,589 m²

What’s proposed

(1) RETAIN DWELLING HOUSE AND BASEMENT AS CONSTRUCTED, (2) PERMISSION TO CONSTRUCT EXTENSION, (3) DECOMMISSION EXISTING SEPTIC TANK AND INSTALL NEW WASTE WATER TREATMENT UNIT AND POLISHING FILTER, ALL IN ACCORDANCE WITH PLANS AND PARTICULARS SUBMITTED

1 other application within 500 m in the last year

Open the report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 9 May 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0114625KY
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

23219 is a planning application to Kerry County Council for (1) retain dwelling house and basement as constructed, (2) permission to construct, received on 28 Feb 2023; permission was granted with conditions on 11 Aug 2023.