PlanningRegister.ie
Kerry County Council · 2460757

Balloonagh Gate Lodge, Balloonagh, Tralee Co. Kerry

Approved in Jan 2025. Building started in 2025, signed off as finished in Dec 2025.

  1. 3 Oct 2024Received
  2. 27 Nov 2024Conditional
  3. 8 Jan 2025Final approval
  4. 5 Aug 2025Building started
  5. 16 Dec 2025Signed off

Planning details

Status
Building started
Decision
Conditional · 27 Nov 2024
Reference
2460757
Received
3 Oct 2024
Site
1,401 m²

What’s proposed

PLANNING PERMISSION FOR; 1 - A CHANGE OF USE FROM OFFICE USE TO A CHILDCARE SERVICE 2 - THE PROVISION OF A NEW FIRE ESCAPE DOOR TO THE NORTH WEST FACADE OF THE EXISTING BUILDING 3 - BLOCKING UP THE EXISTING UTILITY ROOM DOOR WITH MATCHING BLOCKWORK ON THE NORTH EAST FACADE OF THE EXISTING BUILDING 4 - WIDENING OF THE EXISTING DOOR OPE ON THE SOUTH EAST FACADE OF THE EXISTING BUILDING TO FACILITATE A NEW FIRE ESCAPE…

Show all

DOOR 5 - CHANGING THE DIRECTION OF OPENING OF THE EXIT DOOR INTO THE EXISTING COURT YARD 6- INTERNAL ALTERATIONS TO THE EXISTING BUILDING 7- ALL ASSOCIATED SITE WORKS

10 other applications within 500 m in the last year

Open the report

Nearby 10 · 500 m · 12 months

Distance
Time
Show all 10

Explore this area on the map →

Homes nearby

Building started

  • 5 Aug 2025 · Builder told the council work was starting CN0131894KY

Zoning

M1 — Metro / rail economic corridor

A high-density mixed-use employment corridor tied to a rail or metro line. Expect the tallest buildings in the area here.

S1 — Third-level education

Reserved for third-level education institutions.

Protections nearby 250 m

  • NIAH-recorded building · 14
    Saint John's Convent of Mercy; store/warehouse
  • Recorded monument · 2
    Castle - unclassified; R105129
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2460757 is a planning application to Kerry County Council for planning permission for; 1 - a change of use from office use to a childcare service 2 -, received on 3 Oct 2024; permission was granted with conditions on 27 Nov 2024.