Ballinknockane, Camp Tralee, Co. Kerry

Approved in Nov 2026. No sign of building yet.

  1. 15 May 2026Received
  2. 7 Oct 2026Conditional
  3. 10 Nov 2026Final approval
  4. 9 Nov 2031Approval runs out

An email when the builder tells the council work is starting.

Planning details

Status
Approved
Decision
Conditional · 7 Oct 2026
Reference
2660429
Received
15 May 2026
Further information
Requested 9 Jul 2026 · received 10 Sept 2026
Site
2.51 ha

What’s proposed

Remove existing boundary hedgerow between our current playing pitch and field to the north, relocate existing GAA pitch to the north west of our site with the existing ball stop net moved to the north side of the relocated pitch, relocate 6 flood lights previously granted planning under 23/901, erect a new all-weather playing pitch complete with security fence around it and new flood lights to the 4 corners of same…

Show all

erect two portable spectator stands north and south of the new all-weather pitch, construct two new pickle ball courts south east of new all-weather pitch with a security fence around same and two new flood lights east and west of courts, alter existing walking track so that it runs around both the relocated GAA pitch and the new all-weather pitch with associated lighting to light up the track (existing lighting relocated where necessary) complete with all ancillary site works associated with the development

5 other applications within 500 m in five years

Open the free report

Nearby 5 · 500 m · 5 years

Distance
Time

Explore this area on the map →

Homes nearby

Where this comes from

National planning feed (NPAD), fetched 11 Nov 2026, 23:00.

Source: National Planning Application Database · fetched 11 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Nov 2026, 23:00open
Summary

2660429 is a planning application to Kerry County Council for remove existing boundary hedgerow between our current playing pitch and field to the, received on 15 May 2026; permission was granted with conditions on 7 Oct 2026.