PlanningRegister.ie
Kildare County Council · 19336

Moatstown , Milltown , Athy

  1. 29 Mar 2019Received
  2. 23 May 2019Conditional
  3. 1 Jul 2019Final grant
  4. 24 Apr 2022Permission expires
Status
Granted with conditions
Decision
Conditional · 23 May 2019
Council
Kildare County Council
Type
PERMISSION
Site
12.03 ha

What’s proposed

to amend the design of the approved development (Planning Reference 16/1007). Permission is also sought to amend the lifespan of the consented development from 27 years to 35 years. The development will consist of ground mounted solar panel photovoltaic (PV) farm to generate renewable electricity on a 12.02ha site, comprising solar arrays, associated electrical infrastructure, fencing, access improvements and ecologically beneficial landscape works at Moatstown Development Site, Milltown, Athy, Co. Kildare, ITM Grid Reference 665656, 696962, subject to 17 conditions. Amendments proposed are: No changes to red line boundary and no changes to perimeter fence or CCTV points; The height of the solar panels has been increased slightly from 2.3m to 2.5m, their angle span amended from 20-30 degrees to 10-40 degrees. Panels layout has been slightly reconfigured to account for the changes in the height. A slight increase in the overall land take from solar panels; Changes in land take for new access tracks from 3,500sqm to 1,890sqm; Temporary compound area to be moved 60m southwest, but will retain its overall size of 2,800sqm with slight alteration to its overall shape. Compound will be reinstated at the end of the construction phase; Energy Storage Area will be enlarged from 750sqm to 1,265sqm, an increase of 515sqm; Changes from four substations/energy storage containers and one grid connection point to two substations with larger areas of hardstanding and a grid connection point. The land take from the proposed changes is expected to change from 774sqm to 940sqm, an increase of 166sqm; overall decrease in ground disturbance/land take is expected to be approximately 929sqm

19336 is a planning application to Kildare County Council for to amend the design of the approved development (Planning Reference 16/1007). Permission, received on 29 Mar 2019; permission was granted with conditions on 23 May 2019.

Planning details

Reference
19336
Local authority
Kildare County Council
Status
Granted with conditions · register status “APPLICATION FINALISED
Received
29 Mar 2019
Observations close
3 May 2019 (closed 2697 days ago)
Decision due
23 May 2019 · decided 23 May 2019
Decision
Conditional on 23 May 2019
Proposed development
to amend the design of the approved development (Planning Reference 16/1007). Permission is also sought to amend the lifespan of the consented development from 27 years to 35 years. The development will consist of ground mounted solar panel photovoltaic (PV) farm to generate renewable electricity on a 12.02ha site, comprising solar arrays, associated electrical infrastructure, fencing, access improvements and ecologically beneficial landscape works at Moatstown Development Site, Milltown, Athy, Co. Kildare, ITM Grid Reference 665656, 696962, subject to 17 conditions. Amendments proposed are: No changes to red line boundary and no changes to perimeter fence or CCTV points; The height of the solar panels has been increased slightly from 2.3m to 2.5m, their angle span amended from 20-30 degrees to 10-40 degrees. Panels layout has been slightly reconfigured to account for the changes in the height. A slight increase in the overall land take from solar panels; Changes in land take for new access tracks from 3,500sqm to 1,890sqm; Temporary compound area to be moved 60m southwest, but will retain its overall size of 2,800sqm with slight alteration to its overall shape. Compound will be reinstated at the end of the construction phase; Energy Storage Area will be enlarged from 750sqm to 1,265sqm, an increase of 515sqm; Changes from four substations/energy storage containers and one grid connection point to two substations with larger areas of hardstanding and a grid connection point. The land take from the proposed changes is expected to change from 774sqm to 940sqm, an increase of 166sqm; overall decrease in ground disturbance/land take is expected to be approximately 929sqm
As published by the register.
Site area
12.03 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 1 application within 500 m in the last 5 years

Explore this area on the map →

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    • Natural Heritage Area (incl. proposed) · 1
      Grand Canal

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 125886). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/KildareCC/AppFileRefDetails/19336/0.

    Source: npad · fetched 11 Sept 2026, 18:51
    SourceLicenceFetchedLink
    npadCC-BY-4.011 Sept 2026, 18:51open