211470 is a planning application for extension of duration at Confey , Leixlip , Co. Kildare., received by Kildare County Council on 12 Oct 2021 and first seen by Planning Register on 11 Sept 2026. The application describes: Extension of Duration of Planning Ref. No. 16/848 - a solar PV panel array with an export capacity of 10MW comprising approximately 38, 600 photovoltaic panels on ground mounted frames within a site area of 16.91 hectares, 7 No. single storey MV substations, 1 No. single storey DSO substation, 1 No. single storey customer substation, 1 No. single storey spares building, 1 No. communications pole, boundary security fencing, CCTV, associated electrical cabling and ducting, alteration to existing entrance to include access gates and all associated ancillary development works. Revised by Significant Further Information which includes submission of a Natura Impact Statement; submission of road safety audit, swept path analysis and visibility splay drawings; revised location of communications pole as shown on the revised Customer Building Drawing; Revised DSO and MV Building Drawings; Revised Site Layout drawings; Revised Environmental Impact Assessment Screening Report, on land south of the L1015 road. The council refused permission on 2 Dec 2021. The five-week observation window closed on 16 Nov 2021. Within 500 m there are 4 other decided applications in the last five years.
Proposal
Extension of Duration of Planning Ref. No. 16/848 - a solar PV panel array with an export capacity of 10MW comprising approximately 38, 600 photovoltaic panels on ground mounted frames within a site area of 16.91 hectares, 7 No. single storey MV substations, 1 No. single storey DSO substation, 1 No. single storey customer substation, 1 No. single storey spares building, 1 No. communications pole, boundary security fencing, CCTV, associated electrical cabling and ducting, alteration to existing entrance to include access gates and all associated ancillary development works. Revised by Significant Further Information which includes submission of a Natura Impact Statement; submission of road safety audit, swept path analysis and visibility splay drawings; revised location of communications pole as shown on the revised Customer Building Drawing; Revised DSO and MV Building Drawings; Revised Site Layout drawings; Revised Environmental Impact Assessment Screening Report, on land south of the L1015 road
- Status
- APPLICATION FINALISED
- Decision
- Refused on 2 Dec 2021
- Site (from polygon)
- 18.83 ha
- Location precision
- site (coords_polygon)
Timeline
- 12 Oct 2021New applicationObservation window closed 16 Nov 2021
- 2 Dec 2021DecisionAppeal window closed 10 Jan 2022

Full planning report for 53.37787, -6.51147
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- EPA-licensed facility · 3
- Natural Heritage Area (incl. proposed) · 2
- Radon risk area · 3
- Special Area of Conservation · 1
- Recorded monument · 1
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 127447). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/KildareCC/AppFileRefDetails/211470/0.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |