IDA Newbridge Business & Technology Park (Littleconnell) , within the townlands of Greatconnell Littleconnell and Clownings , Newbridge
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
221291 is a planning application for permission at IDA Newbridge Business & Technology Park (Littleconnell) , within the townlands of Greatconnell Littleconnell and Clownings , Newbridge, received by Kildare County Council on 28 Oct 2022 and first seen by Planning Register on 11 Sept 2026. The application describes: for a purpose-built brewery as follows: - Main Brewery Facility (c.9,148m2) including brew house, storage and handling areas, labs, control rooms, workshops, plant rooms/areas (internal and external/roof), storage rooms/areas, process areas and valve blocks, utilities and services areas, circulation, office/admin and welfare facilities, and all associated ancillary areas. Building height ranging up to c.24.3m and including ground floor area (c.7,325m2), part basement (c.72m2), 1st floor (c.1,213m2), 2nd floor (c.270m2) and 3rd floor (c.268m2). Tanker filling station (open area with canopy c.462m2) and raw materials deliveries area (open area with canopy c.138m2 in extent), 92 no. new storage vessels/silos/tanks, with associated access platforms, ranging in height up to c.23.3m. 2 no. external substation buildings (total area 60m2 and building height c.3.8m). Provision of external pipe bridges ranging up to c.7.7m in height. Provision of PV panels on roofs (c.1,171m2 in extent). Provision of external building signage (total area c.12m2). - Renewable Heating Plant Building (c.1,644m2, with height up c.15.9m) including ground floor area (c.1,358m2), part basement (c.286m2) and including internal plant area, turbine room, fuel store, electrical distribution, office/admin areas, externally located Electrostatic Precipitators (ESPs), and 2 no. flue stacks (each c.20m total height). - Utilities Area including Welfare & Control Room building, external electrical plant area, electrical container plant rooms, combined heat and power container plant room (with a flue stack c.11m in total height), fire water tanks (2 no. up to c.4.5m in height) and pump house room. Total floor area of Utilities Area buildings c.142m2 and building height up to c.4.2m. - Wastewater Treatment Plant (WWTP) area with associated tanks (9 no. ranging in height up to c.22.25m) with associated plant rooms/areas (including biogas infrastructure and chemical storage areas), electrical container plant rooms, and dewatering building. Total floor area of WWTP buildings c.55m2 and building height up to c.8.1m. - Water Recycling Plant (WRP) area with main plant building (with external open area with canopy), 2 no. tanks (each c.10m in height), external plant and equipment. Total floor area of WRP buildings c.195m2 and building height up to 7.5m. - Water Treatment Plant (WTP) with 3 no. tanks (ranging in height up to c.17.4m) with associated plant rooms and external plant areas & electrical container. The council granted permission on 28 Mar 2023, with conditions. The five-week observation window closed on 2 Dec 2022. The register records an appeal (ABP-316491-23), decided: conditional. Within 500 m there are 3 other decided applications in the last five years.
Proposal
for a purpose-built brewery as follows: - Main Brewery Facility (c.9,148m2) including brew house, storage and handling areas, labs, control rooms, workshops, plant rooms/areas (internal and external/roof), storage rooms/areas, process areas and valve blocks, utilities and services areas, circulation, office/admin and welfare facilities, and all associated ancillary areas. Building height ranging up to c.24.3m and including ground floor area (c.7,325m2), part basement (c.72m2), 1st floor (c.1,213m2), 2nd floor (c.270m2) and 3rd floor (c.268m2). Tanker filling station (open area with canopy c.462m2) and raw materials deliveries area (open area with canopy c.138m2 in extent), 92 no. new storage vessels/silos/tanks, with associated access platforms, ranging in height up to c.23.3m. 2 no. external substation buildings (total area 60m2 and building height c.3.8m). Provision of external pipe bridges ranging up to c.7.7m in height. Provision of PV panels on roofs (c.1,171m2 in extent). Provision of external building signage (total area c.12m2). - Renewable Heating Plant Building (c.1,644m2, with height up c.15.9m) including ground floor area (c.1,358m2), part basement (c.286m2) and including internal plant area, turbine room, fuel store, electrical distribution, office/admin areas, externally located Electrostatic Precipitators (ESPs), and 2 no. flue stacks (each c.20m total height). - Utilities Area including Welfare & Control Room building, external electrical plant area, electrical container plant rooms, combined heat and power container plant room (with a flue stack c.11m in total height), fire water tanks (2 no. up to c.4.5m in height) and pump house room. Total floor area of Utilities Area buildings c.142m2 and building height up to c.4.2m. - Wastewater Treatment Plant (WWTP) area with associated tanks (9 no. ranging in height up to c.22.25m) with associated plant rooms/areas (including biogas infrastructure and chemical storage areas), electrical container plant rooms, and dewatering building. Total floor area of WWTP buildings c.55m2 and building height up to c.8.1m. - Water Recycling Plant (WRP) area with main plant building (with external open area with canopy), 2 no. tanks (each c.10m in height), external plant and equipment. Total floor area of WRP buildings c.195m2 and building height up to 7.5m. - Water Treatment Plant (WTP) with 3 no. tanks (ranging in height up to c.17.4m) with associated plant rooms and external plant areas & electrical container
- Status
- APPLICATION FINALISED
- Decision
- Conditional on 28 Mar 2023
- Final grant
- 8 Dec 2023
- Permission expires
- 7 Dec 2028
- Site (from polygon)
- 21.60 ha
- Location precision
- site (coords_polygon)
Timeline
- 28 Oct 2022New applicationObservation window closed 2 Dec 2022
- 21 Dec 2022Further information requested
- 3 Feb 2023Further information received
- 28 Mar 2023DecisionAppeal window closed 25 Apr 2023
- 21 Apr 2023Appeal lodged

Full planning report for 53.18789, -6.76533
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
The register records appeal ABP-316491-23 (status unknown) but we have not matched the ACP case yet.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
- Radon risk area · 1
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 129621). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/KildareCC/AppFileRefDetails/221291/0.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |