Kildare Innovation Campus (KIC) , Barnhall Meadows , Leixlip
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
2360047 is a planning application for permission at Kildare Innovation Campus (KIC) , Barnhall Meadows , Leixlip, received by Kildare County Council on 18 Jul 2023 and first seen by Planning Register on 11 Sept 2026. The application describes: will consist of Demolition of existing Buildings No’s 7, 8 and 9 (total gfa c. 84,838sqm). - Existing Buildings No’s 1 – 6 will be retained for deep tech and innovation related uses (total gfa c.42,862sqm) - Construction of 2 no. new deep tech buildings and 4 no. new data centre buildings, all including ancillary office spaces. The deep tech buildings will have an overall maximum height of c.16m and vary in size from30,945sqm – 41,190sqm with a combined total gfa of c. 72,135 sqm. The data centres will be c.15 m in height to parapet and c.16.5m in height to top of roof plant screening. The data centres will vary in size from 13,225 sqm – 21,000 sqm with a combined total gfa of c. 76,225sqm. All buildings will be provided with Solar PV panels at roof level and green walls along selected elevations. - The new deep tech buildings (A1 & A2) will be provided with service yard areas, loading docks, car parking, access roads, security fencing/gates and landscaping. The deep tech buildings will include rainwater harvesting tanks and green roofs over office areas. - Each data centre (B1, C1, C2 & C3) will include data halls, admin blocks (comprising offices, breakroom, loading dock, storage, and ancillary areas) and a variety of mechanical and electrical plant areas/structures including battery storage rooms and mechanical rooms. Car parking, access roads, security fencing/gates, gate houses and landscaping will also be provided. - B1 will include 14 no. fuel oil generators, MV rooms and associated mechanical flues. C1 – C3 will each include 22 no. fuel oil generators, MV rooms and associated mechanical flues (each c.18.6m high). Car parking, access roads, security fencing/gates, gate houses and landscaping will also be provided. - 2 no. district heating pump house areas and inground piping for district heating system. - Construction of a Replacement 110kV Gas Insulated Switchgear (GIS) Substation adjacent to the existing 110kV Rinawade Substation. The current Air Insulated Switchgear (AIS) substation known as the Rinawade 110kV sub is fed by 2 x 110kV Overhead lines. The new substation will connect to these overhead lines via short runs of underground cable. The replacement 110kV substation will include 6 No. transformers, with client control building and a 2 storey GIS substation building within a 2.4m high fenced compound. - Decommissioning and removal of the existing 110kV Rinawade substation. - Construction of an on-site energy centre to provide to the nation. The council granted permission on 7 Sept 2023, with conditions. The five-week observation window closed on 22 Aug 2023. The register records an appeal (ABP-318151-23), decided: conditional. Within 500 m there are 5 other decided applications in the last five years.
Proposal
will consist of Demolition of existing Buildings No’s 7, 8 and 9 (total gfa c. 84,838sqm). - Existing Buildings No’s 1 – 6 will be retained for deep tech and innovation related uses (total gfa c.42,862sqm) - Construction of 2 no. new deep tech buildings and 4 no. new data centre buildings, all including ancillary office spaces. The deep tech buildings will have an overall maximum height of c.16m and vary in size from30,945sqm – 41,190sqm with a combined total gfa of c. 72,135 sqm. The data centres will be c.15 m in height to parapet and c.16.5m in height to top of roof plant screening. The data centres will vary in size from 13,225 sqm – 21,000 sqm with a combined total gfa of c. 76,225sqm. All buildings will be provided with Solar PV panels at roof level and green walls along selected elevations. - The new deep tech buildings (A1 & A2) will be provided with service yard areas, loading docks, car parking, access roads, security fencing/gates and landscaping. The deep tech buildings will include rainwater harvesting tanks and green roofs over office areas. - Each data centre (B1, C1, C2 & C3) will include data halls, admin blocks (comprising offices, breakroom, loading dock, storage, and ancillary areas) and a variety of mechanical and electrical plant areas/structures including battery storage rooms and mechanical rooms. Car parking, access roads, security fencing/gates, gate houses and landscaping will also be provided. - B1 will include 14 no. fuel oil generators, MV rooms and associated mechanical flues. C1 – C3 will each include 22 no. fuel oil generators, MV rooms and associated mechanical flues (each c.18.6m high). Car parking, access roads, security fencing/gates, gate houses and landscaping will also be provided. - 2 no. district heating pump house areas and inground piping for district heating system. - Construction of a Replacement 110kV Gas Insulated Switchgear (GIS) Substation adjacent to the existing 110kV Rinawade Substation. The current Air Insulated Switchgear (AIS) substation known as the Rinawade 110kV sub is fed by 2 x 110kV Overhead lines. The new substation will connect to these overhead lines via short runs of underground cable. The replacement 110kV substation will include 6 No. transformers, with client control building and a 2 storey GIS substation building within a 2.4m high fenced compound. - Decommissioning and removal of the existing 110kV Rinawade substation. - Construction of an on-site energy centre to provide to the nation
- Status
- APPEALED FINANCIAL
- Decision
- Conditional on 7 Sept 2023
- Final grant
- 22 Apr 2024
- Permission expires
- 21 Apr 2029
- Site (from polygon)
- 73.00 ha
- Location precision
- site (coords_polygon)
Timeline
- 18 Jul 2023New applicationObservation window closed 22 Aug 2023
- 7 Sept 2023DecisionAppeal window closed 5 Oct 2023
- 4 Oct 2023Appeal lodged

Full planning report for 53.35475, -6.51477
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
The register records appeal ABP-318151-23 (status unknown) but we have not matched the ACP case yet.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- EPA-licensed facility · 2
- NIAH-recorded building · 1
- Radon risk area · 2
- Recorded monument · 3
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 131731). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/KildareCC/AppFileRefDetails/2360047/0.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |