PlanningRegister.ie
Kildare County Council · 2460364

Maynooth 220kV Substation , Taghadoe , Co. Kildare

  1. 25 Apr 2024Received
  2. 30 May 2024Observations closed
Applications only for this county. Appeals, zoning, RZLT and consultations: Dún Laoghaire-Rathdown and Fingal only for now.
Status
Withdrawn or invalid
Decision
Not yet
Council
Kildare County Council
Type
PERMISSION
Site
20.46 ha

What’s proposed

for the construction of infrastructure, and associated development, at the existing and planned expanded substation, comprising:- •construction of a new 220 kV Gas Insulated Switchgear (GIS) building (83.5m long x 18.5m wide (25.1m including staircases), 17m in height) (1,637 sqm); • construction of a new 110kV GIS building (68.8m x 15.4m, (22m including staircases) 15m in height) (1,138sqm); • both of the GIS Buildings will have 8 no. associated air rods on each of the roofs (3m in height); • construction of 4 no. 220/110kV power transformers to include connections to the new GIS buildings; • 2 no. 220kV and 1 no. 110kV line/cable interface towers and associated removal of 3 no. existing end masts; • 3 no. lightning masts (height 22m); • cable connections to the 220kV GIS building; • new 4.5m wide internal access road and 10 no. new permanent car parking spaces; • associated site excavation, infrastructural and site development works, and above and below ground boundary treatment and landscaping including palisade fencing (2.6m height), lighting and surface water drainage and foul water tank; • associated demolition of existing bungalow farmhouse and agricultural buildings (1,111.6m2 floorspace total) to facilitate the proposed development; and • all ancillary and associated temporary works to facilitate the development at the construction stage, including construction access track, temporary construction compound / site laydown areas and cable connection for the existing Derryiron-Maynooth 110kV overhead line. Planning permission is sought for a period of 10 years. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application

2460364 is a planning application to Kildare County Council for for the construction of infrastructure, and associated development, at the existing and, received on 25 Apr 2024; the file is recorded as incompleted application.

Planning details

Reference
2460364
Local authority
Kildare County Council
Status
Withdrawn or invalid · register status “INCOMPLETED APPLICATION
Received
25 Apr 2024
Observations close
30 May 2024 (closed 837 days ago)
Decision due
No due date published
Decision
Not decided
Proposed development
for the construction of infrastructure, and associated development, at the existing and planned expanded substation, comprising:- •construction of a new 220 kV Gas Insulated Switchgear (GIS) building (83.5m long x 18.5m wide (25.1m including staircases), 17m in height) (1,637 sqm); • construction of a new 110kV GIS building (68.8m x 15.4m, (22m including staircases) 15m in height) (1,138sqm); • both of the GIS Buildings will have 8 no. associated air rods on each of the roofs (3m in height); • construction of 4 no. 220/110kV power transformers to include connections to the new GIS buildings; • 2 no. 220kV and 1 no. 110kV line/cable interface towers and associated removal of 3 no. existing end masts; • 3 no. lightning masts (height 22m); • cable connections to the 220kV GIS building; • new 4.5m wide internal access road and 10 no. new permanent car parking spaces; • associated site excavation, infrastructural and site development works, and above and below ground boundary treatment and landscaping including palisade fencing (2.6m height), lighting and surface water drainage and foul water tank; • associated demolition of existing bungalow farmhouse and agricultural buildings (1,111.6m2 floorspace total) to facilitate the proposed development; and • all ancillary and associated temporary works to facilitate the development at the construction stage, including construction access track, temporary construction compound / site laydown areas and cable connection for the existing Derryiron-Maynooth 110kV overhead line. Planning permission is sought for a period of 10 years. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application
As published by the register.
Site area
20.46 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Around this site this application first, then everything within 500 m

Explore from hereFree report
Click a dot to open its row.
Loading planning applications…
Free · during launch · limited time

Full planning report for 53.34808, -6.60383

Zoning, appeals, sold prices, flood and heritage constraints — everything for this area in one PDF.

No account, no payment. Not a statutory planning search.

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    • Radon risk area · 2
      About 1 in 10 homes in this area is likely to have high radon levels; About 1 in 20 homes in this area is likely to have high radon levels

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 132172). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/KildareCC/AppFileRefDetails/2460364/0.

    Source: npad · fetched 11 Sept 2026, 18:51
    SourceLicenceFetchedLink
    npadCC-BY-4.011 Sept 2026, 18:51open