PlanningRegister.ie
Kilkenny County Council · 17818

IDA , Purcellsinch , Dublin Road

  1. 11 Dec 2017Received
  2. 10 May 2018Conditional
  3. 13 Mar 2024Permission expires
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Appeal decided — other
Decision
Conditional · 10 May 2018
Council
Kilkenny County Council
Type
PERMISSION
Site
1.40 ha

What’s proposed

for development which will consist of the construction of a 100MW Battery Energy Storage System (BESS) with associated balance of plant, equipment and buildings including; a BESS building of 8m height, 82m length and 44m width (comprising on the ground floor a battery rack room, meeting room, Contractor/Storeroom, wet room, UPS room, switch gear room, WC, Transformer rooms, Inverter rooms; and on a mezzanine floor a HVAC/Store room); 2 no. 905m3 firewater storage tanks; an underground 830m3 surface water attenuation tank; an underground 1030m3 firewater retention tank; a 110KV electrical substation and control building of 5.2m height; an access and circulation road with new junction onto an existing IDA private road; footpath, 8 no. car parking spaces; landscaped berm wall up to 2.0m height and native tree and scrub planting, 3m paladin security fence; and all other associated site development works including surface water and foul drainage required to facilitate the developments

17818 is a planning application to Kilkenny County Council for for development which will consist of the construction of a 100MW Battery Energy Storage, received on 11 Dec 2017; permission was granted with conditions on 10 May 2018.

Planning details

Reference
17818
Local authority
Kilkenny County Council
Status
Appeal decided — other · register status “APPLICATION FINALISED”
Received
11 Dec 2017
Observations close
24 Jan 2018 (closed 3169 days ago)
Decision due
13 May 2018 · decided 10 May 2018
Decision
Conditional on 10 May 2018
Proposed development
for development which will consist of the construction of a 100MW Battery Energy Storage System (BESS) with associated balance of plant, equipment and buildings including; a BESS building of 8m height, 82m length and 44m width (comprising on the ground floor a battery rack room, meeting room, Contractor/Storeroom, wet room, UPS room, switch gear room, WC, Transformer rooms, Inverter rooms; and on a mezzanine floor a HVAC/Store room); 2 no. 905m3 firewater storage tanks; an underground 830m3 surface water attenuation tank; an underground 1030m3 firewater retention tank; a 110KV electrical substation and control building of 5.2m height; an access and circulation road with new junction onto an existing IDA private road; footpath, 8 no. car parking spaces; landscaped berm wall up to 2.0m height and native tree and scrub planting, 3m paladin security fence; and all other associated site development works including surface water and foul drainage required to facilitate the developments
As published by the register.
Site area
1.40 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 8 applications within 500 m in the last 5 years

Explore this area on the map →

Homes nearby

Appeal

The register records appeal ABP-301797-18 (status unknown) but we have not matched the ACP case yet.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    C3 — High technology

    Industrial/Technology Park: To provide for industry and information technology related industrial and office development and ancillary services. The purpose is to encourage mainly services type employment on a campus environment

    Zoned for office, research and development and high-technology manufacturing.

    Designations within 250 m

    No OPW flood extent nearby.

    • NIAH-recorded building · 1
      Inch Saw Mills
    • Recorded monument · 5
      Designed landscape - tree-ring; Designed landscape - folly; Kiln - lime

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 384176). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/KilkennyCC/AppFileRefDetails/17818/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open