PlanningRegister.ie
Leitrim County Council · 1845

Boleymaguire and Seltan , Co. Leitrim

  1. 14 Mar 2018Received
  2. 8 May 2018Refused
  3. 14 Mar 2024Permission expires
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Appeal decided — granted
Decision
Refused · 8 May 2018
Council
Leitrim County Council
Type
PERMISSION
Site
5,273 m²

What’s proposed

for the installation of approximately 0.46km of underground cable ducting, 1 no. joint bay and ancillary development laid primarily within the public road corridor, with a section of circa. 0.07km within private lands at Seltan. A Section of ducting is to be installed within a steel box structure to be fixed to Boleymaguire Bridge within the townland of Boleymaguire, Co. Leitrim. Within the townland of Boleymaguire, permission is sought for the carrying out of remedial works to approximately 0.44km of the installed underground cable ducting which is subject to a pending application for Substitute Consent to An Bord Pleanála (Ref: ABP-300811-18), remedial works include the relaying of backfill material. Permission is also sought for the installation of the electricity cable following the completion of the civil works. The development will comprise part of an overall development in Counties Leitrim, Sligo and Roscommon, consisting of the laying of an underground 38 kv electricity cable and associated ducting and ancillary development primarily within the public road to facilitate the connection of the permitted Derrysallagh Wind Farm, Co Sligo (Sligo County Council planning reference: PL 12/133) to the national electricity grid via the existing Garvagh 110kv substation in the townland of Seltan, Co Leitrim. Part of this development is in place and subject to a pending application for Substitute Consent to An Bord Pleanala (ref: ABP-300811-18). This application is accompanied by an Environmental Impact Assessment Report (EIAR)/Environmental Impact Statement (EIS)

1845 is a planning application to Leitrim County Council for for the installation of approximately 0.46km of underground cable ducting, 1 no. joint, received on 14 Mar 2018; permission was refused on 8 May 2018.

Planning details

Reference
1845
Local authority
Leitrim County Council
Status
Appeal decided — granted · register status “APPLICATION FINALISED
Received
14 Mar 2018
Observations close
18 Apr 2018 (closed 3080 days ago)
Decision due
8 May 2018 · decided 8 May 2018
Decision
Refused on 8 May 2018
Proposed development
for the installation of approximately 0.46km of underground cable ducting, 1 no. joint bay and ancillary development laid primarily within the public road corridor, with a section of circa. 0.07km within private lands at Seltan. A Section of ducting is to be installed within a steel box structure to be fixed to Boleymaguire Bridge within the townland of Boleymaguire, Co. Leitrim. Within the townland of Boleymaguire, permission is sought for the carrying out of remedial works to approximately 0.44km of the installed underground cable ducting which is subject to a pending application for Substitute Consent to An Bord Pleanála (Ref: ABP-300811-18), remedial works include the relaying of backfill material. Permission is also sought for the installation of the electricity cable following the completion of the civil works. The development will comprise part of an overall development in Counties Leitrim, Sligo and Roscommon, consisting of the laying of an underground 38 kv electricity cable and associated ducting and ancillary development primarily within the public road to facilitate the connection of the permitted Derrysallagh Wind Farm, Co Sligo (Sligo County Council planning reference: PL 12/133) to the national electricity grid via the existing Garvagh 110kv substation in the townland of Seltan, Co Leitrim. Part of this development is in place and subject to a pending application for Substitute Consent to An Bord Pleanala (ref: ABP-300811-18). This application is accompanied by an Environmental Impact Assessment Report (EIAR)/Environmental Impact Statement (EIS)
As published by the register.
Site area
5,273 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby nothing else within 500 m in the last 5 years

No other application within 500 m in the last 5 years.

Explore this area on the map →

Appeal

The register records appeal ABP-301812-18 (status unknown) but we have not matched the ACP case yet.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    No other designation nearby.

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 399092). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/LeitrimCC/AppFileRefDetails/1845/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open