Kilathmoy Wind Farm Athea Upper, Athea, Co. Limerick
Approved in Mar 2022. No sign of building yet.
Start notices are matched from the national building control register; a start on site can be missed.
- 8 Dec 2021Received
- 10 Feb 2022Conditional
- 16 Mar 2022Final approval
- 15 Mar 2027Approval runs out
Planning details
- Status
- Approved
- Decision
- Conditional · 10 Feb 2022
- Reference
- 211702
- Received
- 8 Dec 2021
- Site
- 1.02 ha
What’s proposed
An extension of the existing battery energy storage system (BESS) at Kilathmoy Wind Farm substation. The proposed development will consist of the following components; Lithium-ion battery containers including ancillary HVAC equipment; Power Conversion System (PCS)/Inverter units; Transformer units;
Show all
Connection to the existing on site Grid Transformer, Prefabricated equipment container (switchgear and controls), back up generator, auxiliary transformer, underground cabling and associated infrastructure including compound lighting, security fencing and CCTV system, all as detailed on the planning application drawings. A Natura Impact Statement(NIS) has been completed and submitted with this application
1 other application within 500 m in the last year
Open the reportNearby 1 · 500 m · 12 months
Homes nearby
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
211702 is a planning application to Limerick City and County Council for an extension of the existing battery energy storage system (BESS) at Kilathmoy Wind Farm, received on 8 Dec 2021; permission was granted with conditions on 10 Feb 2022.