PlanningRegister.ie
Louth County Council · 17403

Annaloughan, Jenkinstown, Dundalk

Approved in 2017. Building started in 2018.

  1. 29 May 2017Received
  2. 3 Nov 2017Conditional
  3. 4 Dec 2017Final approval
  4. 10 Sept 2018Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Building startedi
Decision
Conditional · 3 Nov 2017
Council
Louth County Council
Type
PERMISSION
Units
1
Site
99 m²

Live near Annaloughan?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Permission for development that consists of one dwelling house, waste water treatment system and all associated site works

Planning details

Reference
17403
Local authority
Louth County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
29 May 2017
Observations close
3 Jul 2017 (closed 3382 days ago)
Decision due
8 Nov 2017 · decided 3 Nov 2017
Decision
Conditional on 3 Nov 2017
Proposed development
Permission for development that consists of one dwelling house, waste water treatment system and all associated site works
As published by the register.
Site area
99 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 5 · 500 m · 5 years

Explore this area on the map →

Homes nearby

Building started

  • 10 Sept 2018 · Builder told the council work was starting (opted out of the finish sign-off) CN0043483LH

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

  • Recorded monument · 6
    Ringfort - rath; Souterrain

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

17403 is a planning application to Louth County Council for permission for development that consists of one dwelling house, waste water treatment, received on 29 May 2017; permission was granted with conditions on 3 Nov 2017.