  1. 23 Mar 2022Received
  2. 15 Aug 2023Conditional
  3. 15 Aug 2028Approval runs out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 15 Aug 2023
Council
Louth County Council
Type
PERMISSION
Units
207
Site
13.24 ha

Live near Bridgegate Rathgory Mulladrillen?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

SHD Stage 3 Decision made by ABP (ABP-313083-22) Stage 2 Ref. No. 20/759 - See www.bridgegateshd.ie for details. The Ardee Partnership, intend to apply to An Bord Pleanála for permission. development will consist of:A) construction of 272 no. residential units comprising 206 houses 66 no. duplex units (3 storeys), with private open space, B) A part 1, part 2 no. storey crèche and playground and a single storey community building adjacent at a community hubaccessed from Bridgegate Avenue served by car parking on Bridgegate Green and Bridgegate Avenue;C) A Park located in the northof the site extending to accessed from community hub and between duplex B & C at Bridgegate Avenue, with 2 no. pedestrian links to public park adjoining to the west and 1 no. pedestrian footpathextending to the north perimeter at Hale Street, with reservation for a future link road to the east facilitated in the north section of park;D) Works to the Rathgory Tributary comprising realignment of the channel and regrading and reprofiling of land, implementation of 2 vehicular crossings and provision of a riparian corridor based around the open watercourse comprising landscaping and planting with access to the watercourse provided for maintenance purposes and 1 no. pedestrian and cyclist crossing; E) A series of public open spaces; open spaces will provide a mix of hard and soft landscaping, pedestrian and cycle access and a range of activities F) Provision of shared surfaces, landscaped streetscapes including planting and landscaping at two neighbourhood streets in the southern part of the site, with roads provided to site boundaries to the east, south and west to facilitate possible future connections; G) All landscaping and boundary treatments;H) Roads and access infrastructure taken from Bridgegate Avenue (permitted Ref: 10/174; ABP Ref: PL15.238053, provision of a bus stop on the south side of Bridgegate Avenue adjacent to community hub and provision of cycle lanes at thislocation (continued through Public Open Space 01); a total of 480 no. car parking spaces (362 no. serving houses, 84 no. serving duplexes, 23 no. serving crèche and community building and 11 no. visitor and public open spaces), a total of 296 no. bicycle parking spaces ;I) Provision of 2 ESB substations, drainage and services infrastructure, lighting, SUDS drainage. An EIAR and a NIS have been prepared

Planning details

Reference
22228
Local authority
Louth County Council
Status
Granted with conditions · register status “DECISION MADE”
Received
23 Mar 2022
Observations close
27 Apr 2022 (closed 1623 days ago)
Decision due
31 May 2025 · decided 15 Aug 2023
Decision
Conditional on 15 Aug 2023
Proposed development
SHD Stage 3 Decision made by ABP (ABP-313083-22) Stage 2 Ref. No. 20/759 - See www.bridgegateshd.ie for details. The Ardee Partnership, intend to apply to An Bord Pleanála for permission. development will consist of:A) construction of 272 no. residential units comprising 206 houses 66 no. duplex units (3 storeys), with private open space, B) A part 1, part 2 no. storey crèche and playground and a single storey community building adjacent at a community hubaccessed from Bridgegate Avenue served by car parking on Bridgegate Green and Bridgegate Avenue;C) A Park located in the northof the site extending to accessed from community hub and between duplex B & C at Bridgegate Avenue, with 2 no. pedestrian links to public park adjoining to the west and 1 no. pedestrian footpathextending to the north perimeter at Hale Street, with reservation for a future link road to the east facilitated in the north section of park;D) Works to the Rathgory Tributary comprising realignment of the channel and regrading and reprofiling of land, implementation of 2 vehicular crossings and provision of a riparian corridor based around the open watercourse comprising landscaping and planting with access to the watercourse provided for maintenance purposes and 1 no. pedestrian and cyclist crossing; E) A series of public open spaces; open spaces will provide a mix of hard and soft landscaping, pedestrian and cycle access and a range of activities F) Provision of shared surfaces, landscaped streetscapes including planting and landscaping at two neighbourhood streets in the southern part of the site, with roads provided to site boundaries to the east, south and west to facilitate possible future connections; G) All landscaping and boundary treatments;H) Roads and access infrastructure taken from Bridgegate Avenue (permitted Ref: 10/174; ABP Ref: PL15.238053, provision of a bus stop on the south side of Bridgegate Avenue adjacent to community hub and provision of cycle lanes at thislocation (continued through Public Open Space 01); a total of 480 no. car parking spaces (362 no. serving houses, 84 no. serving duplexes, 23 no. serving crèche and community building and 11 no. visitor and public open spaces), a total of 296 no. bicycle parking spaces ;I) Provision of 2 ESB substations, drainage and services infrastructure, lighting, SUDS drainage. An EIAR and a NIS have been prepared
As published by the register.
Site area
13.24 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 11 · 500 m · 5 years

Show all 11

Explore this area on the map →

Homes nearby

Zoning

O1 — Green belt and strategic open land

Land zoned to keep urban areas apart. Development is strongly resisted.

R1 — New residential

Zoned for new residential communities. This is where large housing schemes are expected to go, subject to the social and physical infrastructure arriving with them.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

No mapped flood area nearby.

  • Recorded monument · 4
    Souterrain; Earthwork

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

22228 is a planning application to Louth County Council for SHD Stage 3 Decision made by ABP (ABP-313083-22) Stage 2 Ref. No. 20/759 - See, received on 23 Mar 2022; permission was granted with conditions on 15 Aug 2023.