Mayo County Council · 1731
Raheen Barr/Claggan/Derrynadivva, Castlebar, Co. Mayo
Approved in Apr 2017. The approval ran out in 2022.
- 24 Jan 2017Received
- 16 Mar 2017Conditional
- 20 Apr 2017Final approval
- 19 Apr 2022Approval ran out
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
- Status
- Approved
- Decision
- Conditional · 16 Mar 2017
- Council
- Mayo County Council
- Type
- PERMISSION
- Site
- 49.31 ha
Live near Raheen Barr/Claggan/Derrynadivva?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
PERMISSION FOR CONTINUANCE OF USE OF THE ALREADY PERMITTED WINDFARM CONSISTING OF 22 NO. VESTAS V52 WIND TURBINES, ACCESS ROADS, SUBSTATION AND ANCILLARY SITE WORKS
Planning details
- Reference
- 1731
- Local authority
- Mayo County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 24 Jan 2017
- Observations close
- 28 Feb 2017 (closed 3510 days ago)
- Decision due
- 20 Mar 2017 · decided 16 Mar 2017
- Decision
- Conditional on 16 Mar 2017
- Proposed development
- PERMISSION FOR CONTINUANCE OF USE OF THE ALREADY PERMITTED WINDFARM CONSISTING OF 22 NO. VESTAS V52 WIND TURBINES, ACCESS ROADS, SUBSTATION AND ANCILLARY SITE WORKSAs published by the register.
- Site area
- 49.31 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby none · 500 m · 5 years
No other application within 500 m in the last 5 years.
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
Nothing else protected nearby.
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
1731 is a planning application to Mayo County Council for permission for continuance of use of the already permitted windfarm consisting of 22 no., received on 24 Jan 2017; permission was granted with conditions on 16 Mar 2017.