PlanningRegister.ie
Mayo County Council · 19777

Foxford Water Treatment Plant, Foxford, Co. Mayo

Approved in Jan 2020. Building started in 2021.

  1. 2 Oct 2019Received
  2. 19 Dec 2019Conditional
  3. 31 Jan 2020Final approval
  4. 4 Aug 2021Building started
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Building startedi
Decision
Conditional · 19 Dec 2019
Council
Mayo County Council
Type
PERMISSION
Site
1,597 m²

Live near Foxford Water Treatment Plant?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

INSTALLATION OF TWO NEW CONTINUOUS SAND FILTERS TO REPLACE THE EXISTING SAND FILTERS, INSTALLATION OF TWO NEW CHEMICAL STORAGE TANKS, CONVERSION OF THE EXISTING SLOW SAND FILTER TO A STORAGE RESERVOIR, THE INSTALLATION OF A NEW KIOSK TO HOUSE CONTROL EQUIPMENT, THE INSTALLATION OF A NEW BOUNDARY FENCE AND ALL ANCILLARY SITE WORKS

Planning details

Reference
19777
Local authority
Mayo County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
2 Oct 2019
Observations close
6 Nov 2019 (closed 2534 days ago)
Decision due
4 Jan 2020 · decided 19 Dec 2019
Decision
Conditional on 19 Dec 2019
Site area
1,597 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 4 · 500 m · 5 years

Explore this area on the map →

Homes nearby

Building started

  • 4 Aug 2021 · Builder told the council work was starting (seven-day notice) SN0006431MO

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

Nothing else protected nearby.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

19777 is a planning application to Mayo County Council for installation of two new continuous sand filters to replace the existing sand filters, received on 2 Oct 2019; permission was granted with conditions on 19 Dec 2019.