PlanningRegister.ie
Mayo County Council · 25293

Derrew, Ballyheane, Castlebar

Approved in Nov 2025. Building started in 2026.

  1. 21 Jul 2025Received
  2. 17 Oct 2025Conditional
  3. 17 Nov 2025Final approval
  4. 26 Feb 2026Building started

Planning details

Status
Building startedi
Decision
Conditional · 17 Oct 2025
Reference
25293
Received
21 Jul 2025
Further information
Requested 11 Sept 2025 · received 23 Sept 2025
Units
1
Site
3,869 m²

What’s proposed

Construction of a new dwelling, domestic garage, effluent treatment unit and percolation area with associated site works

1 other application within 500 m in the last year

Open the report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 26 Feb 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0138893MO
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

25293 is a planning application to Mayo County Council for construction of a new dwelling, domestic garage, effluent treatment unit and percolation, received on 21 Jul 2025; permission was granted with conditions on 17 Oct 2025.