Approved in Apr 2022. Building started in 2022.

  1. 15 Dec 2021Received
  2. 16 Feb 2022Conditional
  3. 1 Apr 2022Final approval
  4. 27 Jun 2022Building started

Planning details

Status
Building startedi
Decision
Conditional · 16 Feb 2022
Reference
212341
Received
15 Dec 2021
Site
3.81 ha

What’s proposed

The development will consist of an expansion of the existing Facility, which includes; 1) construction of a single storey building, with an approximate gross floor area of 1.946 sqm, on land adjacent to the west of the existing Facility, where same building shall accommodate a reverberatory furnace, casting machine and associated production line, storage and loading areas and air abatement infrastructure.

Show all

The reverberatory furnace will have a capacity of 25 tonnes per day, 2) construction of 22m high emission stack to be located adjacent to the existing 22m high emission stack, 3) provision of additional yard space and vehicle access ramp to/from the existing yard, 4) provision of stormwater attenuation unit and associated drainage and treatment infrastructure to cater for proposed building and proposed yard, 5) construction of additional staff welfare facilities building, 6) provision of staff and visitor car park comprising 52 no. spaces to serve P. Carney Limited to be located to the south-east of the Facility including associated stormwater drainage and treatment infrastructure, and including provision of private direct pedestrian access path to the Facility. Vehicular access to the car park will be via the existing Vartane Limited access onto the R154, Kilskeer road, 7) demolition of shed with an approximate gross floor area of 233 sqm, 8) provision of temporary access including sightline works, from the L1633, Collinstown Road, for the duration of construction works, to provide for construction traffic access/egress. This access will be removed following completion of the works, 9) construction of lined firewater retention pond, 10) landscaping works, 11) all ancillary site development works. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application. This development requires an Industrial Emissions (IE) Licence, under the Environmental Protection Act 1992, as amended, which will be ought through a licence review application of the existing Integrated Pollution Control (IPC) Licence (Reg. no. P0402-02)

2 other applications within 500 m in the last year

Open the report

Nearby 2 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Building started

  • 27 Jun 2022 · Builder told the council work was starting (seven-day notice) SN0007407MH

Zoning

C2.1 — Economic development and employment

Zoned for employment uses. Housing is not the intended use here.

M2 — Major town centre

The main town centre — retail, offices, civic uses, apartments.

P5 — Rural and agricultural

Land zoned to stay rural. New houses are restricted to demonstrated local need under the rural-housing policy of the development plan.

S5 — Sustainable neighbourhood infrastructure

Reserved for the schools, creches, community and health facilities a neighbourhood needs.

Protections nearby 250 m

  • NIAH-recorded building · 6
    The Old Barracks; Hill House
  • Recorded monument · 2
    Barrow - mound barrow; R172635
Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

212341 is a planning application to Meath County Council for the development will consist of an expansion of the existing Facility, which includes, received on 15 Dec 2021; permission was granted with conditions on 16 Feb 2022.