What’s proposed

The development consists of land recovery operation (being) reclamation of agricultural land and all associated site works comprising of the importation of natural materials of clay, silt, sand, gravel or stone and which comes within the meaning of inert waste, through deposition for the purposes of the improvement or development of land Class 5 of the waste management (Facility Permit and Registration) Regulations…

Show all

2007-2008. A 5 year planning permission is requested and during the duration of this period 62,490 tons of inert soil and stone will be imported for the purpose of land reclamation. Entrance to the site will be via the existing farm road on adjoining site the subject of current Planning RA/170057 and WFP-MH17/0006/01

  1. 8 Jun 2022Received
  2. 3 Nov 2022Conditional
  3. 16 Dec 2022Final approval
  4. 15 Dec 2027Approval runs out

An email when the builder tells the council work is starting.

Planning details

Status
Approved
Decision
Conditional · 3 Nov 2022
Reference
22752
Received
8 Jun 2022
Further information
Requested 29 Jul 2022 · received 11 Oct 2022
Site
78 m²

1 other application within 500 m in the last year · 1 open for comments

Get the full report

Nearby 1 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Zoning

P5 — Rural and agricultural

Land zoned to stay rural. New houses are restricted to demonstrated local need under the rural-housing policy of the development plan.

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

22752 is a planning application to Meath County Council for the development consists of land recovery operation (being) reclamation of agricultural, received on 8 Jun 2022; permission was granted with conditions on 3 Nov 2022.