Killary Lobinstown Navan , & Rathkenny , Navan Co. Meath
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
231082 is a planning application for permission at Killary Lobinstown Navan , & Rathkenny , Navan Co. Meath, received by Meath County Council on 27 Nov 2023 and first seen by Planning Register on 11 Sept 2026. The application describes: the development will consist of a 10-year permission for the construction of a solar PV energy development within a total site area of approximately 131.93ha, to include solar PV panels ground mounted on steel support structures, electrical transformer/inverter station modules, storage containers, CCTV cameras, access tracks, fencing and associated electrical cabling, ducting and ancillary infrastructure. A Natura Impact Statement accompanies this application. Significant further information/revised plans submitted on this application. The council granted permission on 13 Sept 2024, with conditions. The five-week observation window closed on 10 Jan 2024. The register records an appeal (ABP-321002-24), decided: modified. Within 500 m there is 1 other decided application in the last five years.
Proposal
the development will consist of a 10-year permission for the construction of a solar PV energy development within a total site area of approximately 131.93ha, to include solar PV panels ground mounted on steel support structures, electrical transformer/inverter station modules, storage containers, CCTV cameras, access tracks, fencing and associated electrical cabling, ducting and ancillary infrastructure. A Natura Impact Statement accompanies this application. Significant further information/revised plans submitted on this application
- Status
- APPLICATION FINALISED
- Decision
- Conditional on 13 Sept 2024
- Permission expires
- 4 Nov 2035
- Site (from polygon)
- 132.32 ha
- Location precision
- site (coords_polygon)
Timeline
- 27 Nov 2023New applicationObservation window closed 10 Jan 2024
- 29 Jan 2024Further information requested
- 29 Jul 2024Further information received
- 13 Sept 2024DecisionAppeal window closed 11 Oct 2024
- 8 Oct 2024Appeal lodged

Full planning report for 53.76926, -6.65489
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
The register records appeal ABP-321002-24 (status unknown) but we have not matched the ACP case yet.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 140431). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/MeathCC/AppFileRefDetails/231082/0.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|