Staleen Water Treatment Plant , Stalleen , Donore Co. Meath
Data updated 12 Sept 2026 · register lag up to 7 days · sources & freshness
2661039 is a planning application for permission at Staleen Water Treatment Plant , Stalleen , Donore Co. Meath, received by Meath County Council on 18 Aug 2026 and first seen by Planning Register on 11 Sept 2026. The application describes: the proposed development consists of: A) Treatment Process Upgrades: i) Introduction of tertiary treatment on final water to improve water quality, comprising activated carbon dosing, a contact tank, a batching system, and dual storage silos; ii) Interconnecting pipelines; and iii) Sludge Treatment Enhancements comprising: a) Construction of two new washwater recovery tanks; b) Installation of new sludge pumps, return pipelines and decant systems; c) Construction of a new sludge thickening tank; d) Installation of a second sludge plate press and upgraded feed pumps; e) Extension of the sludge dewatering building; f) Replacement and upsizing of sludge pipelines. B) General Site Improvements: i) Upgrades to walkways, stairs, footpaths, and general safe access areas; ii) Improved chemical storage facilities (additional tank) with enhanced ventilation and heating; iii) Refurbishment of the backwash/blower room and relocation of electrical panels; iv) Installation of ground mounted and rooftop solar PV panels to reduce energy consumption and enhance sustainability; and v) Demolition of existing flocculation tank. No decision has been made yet; the council's decision is due by 12 Oct 2026. Observations can be made to the council until 22 Sept 2026 (10 days left) under s.34 of the Planning and Development Act 2000.
Proposal
the proposed development consists of: A) Treatment Process Upgrades: i) Introduction of tertiary treatment on final water to improve water quality, comprising activated carbon dosing, a contact tank, a batching system, and dual storage silos; ii) Interconnecting pipelines; and iii) Sludge Treatment Enhancements comprising: a) Construction of two new washwater recovery tanks; b) Installation of new sludge pumps, return pipelines and decant systems; c) Construction of a new sludge thickening tank; d) Installation of a second sludge plate press and upgraded feed pumps; e) Extension of the sludge dewatering building; f) Replacement and upsizing of sludge pipelines. B) General Site Improvements: i) Upgrades to walkways, stairs, footpaths, and general safe access areas; ii) Improved chemical storage facilities (additional tank) with enhanced ventilation and heating; iii) Refurbishment of the backwash/blower room and relocation of electrical panels; iv) Installation of ground mounted and rooftop solar PV panels to reduce energy consumption and enhance sustainability; and v) Demolition of existing flocculation tank
- Status
- PRE_VALIDATION
- Decision
- N/a
- Site (from polygon)
- 2.61 ha
- Location precision
- site (coords_polygon)
Timeline
- 18 Aug 2026Decision
- 18 Aug 2026New applicationObservation window closes 22 Sept 2026

Full planning report for 53.68683, -6.42627
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
- Radon risk area · 1
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 146780). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/MeathCC/AppFileRefDetails/2661039/0.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |