PlanningRegister.ie
Offaly County Council · 20223

Ballindown Bogderriesballywilliam, and Ballynaguilsha, Co Offaly

Withdrawn.

  1. 16 Jun 2020Received
  2. 21 Jul 2020Observations closed
Status
Withdrawn or invalid
Decision
Not yet
Council
Offaly County Council
Type
PERMISSION
Site
71.07 ha

Live near Ballindown Bogderriesballywilliam?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

THE CONSTRUCTION OF A SOLAR PV DEVELOPMENT WITH A MAXIMUM EXPORT CAPACITY (MEC) OF UP TO 40MW COMPRISING OF A CA. 122,904 NO. PHOTOVOLTAIC PANELS LAID OUT IN ARRAYS, THE CONSTRUCTION OF A 38KV SUBSTATION (CA.114.4M2 X 4.75M TALL), A TRANSFORMER UNIT (CA.18M2 X 4M TALL) AND ASSOCIATED BUND, ALONG WITH ANCILLARY DEVELOPMENT INCLUDING: 16 NO. POWER HUBS (CA. 15.25M2 X 2.4M), WHICH INCORPORATE AN INVERTER AND A TRANSFORMER, 1 NO. SINGLE STOREY COMMUNICATIONS BUILDING ( 11.1M2 X 2.5M), 1 NO. SINGLE STOREY CLIENT SIDE SUB-STATION (15.25M2 X 2.9M), 1 NO. SINGLE STOREY EQUIPMENT STORAGE BUILDING (7.5M2 X 2.7M), 10 NO. CCTV CAMERAS MOUNTED ON 4M HIGH POLES, PERIMETER SECURITY FENCING AND ALL ANCILLARY WORKS. THE TOTAL DEVELOPMENT AREA WILL BE CA 70.2HA

Planning details

Reference
20223
Local authority
Offaly County Council
Status
Withdrawn or invalid · register status “DEEMED WITHDRAWN”
Received
16 Jun 2020
Observations close
21 Jul 2020 (closed 2278 days ago)
Decision
Not decided
Site area
71.07 ha from the mapped boundary, not the council's figure

Nearby none · 500 m · 5 years

No other application within 500 m in the last 5 years.

Explore this area on the map →

Protections nearby 250 m

  • Recorded monument · 2
    Enclosure; R141523

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

20223 is a planning application to Offaly County Council for the construction of a solar pv development with a maximum export capacity (mec) of up to, received on 16 Jun 2020; the file is recorded as deemed withdrawn.