  1. 13 Oct 2020Received
  2. 26 Apr 2021Conditional
  3. 15 Jun 2021Final grant
  4. 14 Jun 2031Permission expires
Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Granted with conditions
Decision
Conditional · 26 Apr 2021
Council
Offaly County Council
Type
PERMISSION
Units
1
Site
130.84 ha

What’s proposed

A 10-YEAR PERMISSION. THE DEVELOPMENT WILL CONSIST OF THE CONSTRUCTION OF: 1. A SOLAR PV DEVELOPMENT ON A C.132 HA SITE CONSISTING OF SOLAR PANELS ON GROUND-MOUNTED FRAMES, 27 NO. SINGLE STOREY ELECTRICAL INVERTER/ TRANSFORMER UNITS, SECURITY FENCING, CCTV SYSTEM WITH POLE MOUNTED CAMERAS, UPGRADING OF EXISTING ACCESS, LANDSCAPING AND ALL ASSOCIATED ANCILLARY DEVELOPMENT WORKS; 2. AN ENCLOSED BATTERY ENERGY STORAGE SYSTEM COMPOUND ON A C.0.385 HA LOCATED WITHIN THE SOLAR PV DEVELOPMENT SITE CONSISTING OF 18 NO. BATTERY STORAGE UNITS (EACH WITH ASSOCIATED CONTAINERISED STEP UP TRANSFORMER), 1 NO. CONTAINERISED CONTROL ROOM AND 1 NO. CONTAINERISED SWITCH ROOM AND ALL ASSOCIATED ANCILLARY DEVELOPMENT WORKS; AND 3. A TEMPORARY CONSTRUCTION COMPOUND ADJACENT TO THE EXISTING ACCESS. THE OPERATIONAL LIFESPAN OF THE SOLAR PV DEVELOPMENT AND BATTERY ENERGY STORAGE SYSTEM WILL BE 35 YEARS. A NATURA IMPACT STATEMENT (NIS) WILL ACCOMPANY THE PLANNING APPLICATION

20494 is a planning application to Offaly County Council for a 10-YEAR PERMISSION. THE DEVELOPMENT WILL CONSIST OF THE CONSTRUCTION OF: 1. A SOLAR PV, received on 13 Oct 2020; permission was granted with conditions on 26 Apr 2021.

Planning details

Reference
20494
Local authority
Offaly County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
13 Oct 2020
Observations close
17 Nov 2020 (closed 2141 days ago)
Decision due
26 Apr 2021 · decided 26 Apr 2021
Decision
Conditional on 26 Apr 2021
Proposed development
A 10-YEAR PERMISSION. THE DEVELOPMENT WILL CONSIST OF THE CONSTRUCTION OF: 1. A SOLAR PV DEVELOPMENT ON A C.132 HA SITE CONSISTING OF SOLAR PANELS ON GROUND-MOUNTED FRAMES, 27 NO. SINGLE STOREY ELECTRICAL INVERTER/ TRANSFORMER UNITS, SECURITY FENCING, CCTV SYSTEM WITH POLE MOUNTED CAMERAS, UPGRADING OF EXISTING ACCESS, LANDSCAPING AND ALL ASSOCIATED ANCILLARY DEVELOPMENT WORKS; 2. AN ENCLOSED BATTERY ENERGY STORAGE SYSTEM COMPOUND ON A C.0.385 HA LOCATED WITHIN THE SOLAR PV DEVELOPMENT SITE CONSISTING OF 18 NO. BATTERY STORAGE UNITS (EACH WITH ASSOCIATED CONTAINERISED STEP UP TRANSFORMER), 1 NO. CONTAINERISED CONTROL ROOM AND 1 NO. CONTAINERISED SWITCH ROOM AND ALL ASSOCIATED ANCILLARY DEVELOPMENT WORKS; AND 3. A TEMPORARY CONSTRUCTION COMPOUND ADJACENT TO THE EXISTING ACCESS. THE OPERATIONAL LIFESPAN OF THE SOLAR PV DEVELOPMENT AND BATTERY ENERGY STORAGE SYSTEM WILL BE 35 YEARS. A NATURA IMPACT STATEMENT (NIS) WILL ACCOMPANY THE PLANNING APPLICATION
As published by the register.
Site area
130.84 ha from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 2 applications within 500 m in the last 5 years

Explore this area on the map →

Appeal

Not appealed.

Commencement

No commencement notice matched to this reference.

    Zoning at the site

    No zoning objective covers this site in the current plan.

    Designations within 250 m

    No OPW flood extent nearby.

    • Recorded monument · 6
      Earthwork; Enclosure; Bullaun stone

    Provenance

    Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 446523). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/OffalyCC/AppFileRefDetails/20494/0.

    Source: npad · fetched 18 Sept 2026, 15:44
    SourceLicenceFetchedLink
    npadCC-BY-4.018 Sept 2026, 15:44open