Approved in Mar 2023. Building started in 2024.

  1. 21 Dec 2022Received
  2. 23 Feb 2023Conditional
  3. 30 Mar 2023Final approval
  4. 16 May 2024Building started

Planning details

Status
Building startedi
Decision
Conditional · 23 Feb 2023
Reference
22664
Received
21 Dec 2022
Site
1.05 ha

What’s proposed

EIRGRID PLC (WITH THE CONSENT AND APPROVAL OF THE ELECTRICITY SUPPLY BOARD (ESB)), INTENDS TO APPLY FOR PERMISSION FOR DEVELOPMENT AT SITE OF APPROXIMATELY 1 HECTARE AT DERRYIRON 110KV SUBSTATION, CLONIN, RHODE, CO. OFFALY.

Show all

DEVELOPMENT CONSISTING OF WORKS TO UPGRADE THE EXISTING SUBSTATION INCLUDING: THE INSTALLATION OF ADDITIONAL AIR INSULATED SWITCHGEAR ELECTRICAL APPARATUS (APPROXIMATELY 7M IN HEIGHT) TO FACILITATE THE PROVISION OF A 110KV BUSBAR; INSTALLATION OF 3 NO. ADDITIONAL BAYS (EACH CONSISTING OF BUSBAR DISCONNECTS, SECTIONALISERS, CIRCUIT BREAKERS, CURRENT TRANSFORMERS, VOLTAGE TRANSFORMERS, LINE TRAPS, COUPLING CAPACITORS AND OTHER ELECTRICAL APPARATUS); AN EXTENSION TO THE NORTH OF THE EXISTING CONTROL BUILDING (APPROXIMATELY 73 SQUARE METERS) TO PROVIDE ACCOMMODATION FOR CABINETS, OTHER ELECTRICAL APPARATUS AND A BATTERY ROOM; INSTALLATION OF 2 NO. CIRCUIT BYPASS ARRANGEMENTS (APPROXIMATELY 14M AND APPROXIMATELY 4M IN HEIGHT, RESPECTIVELY) TO FACILITATE NORMAL OPERATION OF THE SUBSTATION DURING CONSTRUCTION; AND AN EXTENSION TO THE HARDSTAND COMPOUND (APPROXIMATELY 0.03 HECTARES). THE DEVELOPMENT WILL ALSO CONSIST OF: ALL ANCILLARY AND ASSOCIATED ELECTRICAL WORKS TO FACILITATE THE PROPOSED DEVELOPMENT; AND ALL OTHER ASSOCIATED SITE EXCAVATION, INFRASTRUCTURAL AND SITE DEVELOPMENT WORKS ABOVE AND BELOW GROUND, INCLUDING SITE PREPARATION WORKS, SITE CLEARANCE AND LEVELLING; HARDSTANDING, INTERNAL ACCESS TRACKS AND TEMPORARY CONSTRUCTION COMPOUND; EARTHGRID, SURFACE WATER DRAINAGE NETWORK; PALISADE FENCING (APPROXIMATELY 2.7M HIGH) AND GATES; AND LANDSCAPING

5 other applications within 500 m in the last year · 1 open for comments

Open the report

Nearby 5 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 16 May 2024 · Builder told the council work was starting (seven-day notice) SN0010358OY
Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

22664 is a planning application to Offaly County Council for eirgrid plc (with the consent and approval of the electricity supply board (esb)), received on 21 Dec 2022; permission was granted with conditions on 23 Feb 2023.