PlanningRegister.ie
Offaly County Council · 2460002

Derrynagall or Ballydaly, Tullamore, Co. Offaly

Approved in May 2024. No sign of building yet.

Start notices are matched from the national building control register; a start on site can be missed.

  1. 4 Jan 2024Received
  2. 17 Apr 2024Conditional
  3. 27 May 2024Final approval
  4. 26 May 2034Approval runs out

An email when the builder tells the council work is starting.

Planning details

Status
Approved
Decision
Conditional · 17 Apr 2024
Reference
2460002
Received
4 Jan 2024
Further information
Requested 28 Feb 2024 · received 21 Mar 2024
Site
3.20 ha

What’s proposed

A 10 year planning permission. The development will consist of a grid system services facility within a total site area of 3.5 hectares. The proposed development will have a projected life span of 30 years.

Show all

The development will include 1 no. single storey electrical substation building, 1 no. customer substation control and switch rooms, up to 20 no. electrical inverter/transformer station modules mounted on concrete plinths, up to 80 no. containerised battery blocks on concrete support structures and associated heating, ventilation and air conditioning units (HVAC units), access tracks and upgraded site entrance, associated electrical cabling and ducting, security gates and perimeter security fencing up to 2.6m palisade fencing, CCTV security monitoring system, landscaping works and all associated ancillary infrastructure

4 other applications within 500 m in the last year

Open the report

Nearby 4 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2460002 is a planning application to Offaly County Council for a 10 year planning permission. The development will consist of a grid system services, received on 4 Jan 2024; permission was granted with conditions on 17 Apr 2024.