Approved in Oct 2025. Building started in 2026.

  1. 26 Feb 2025Received
  2. 4 Sept 2025Conditional
  3. 9 Oct 2025Final approval
  4. 13 Feb 2026Building started
Status
Building startedi
Decision
Conditional · 4 Sept 2025
Council
Offaly County Council
Type
PERMISSION
Units
1
Site
431 m²

What’s proposed

the development consisting of knocking an existing extension and rebuilding a new extension

Planning details

Reference
2560046
Local authority
Offaly County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
26 Feb 2025
Decision due
4 Sept 2025 · decided 4 Sept 2025
Decision
Conditional on 4 Sept 2025
Site area
431 m² from the mapped boundary, not the council's figure

Live near No. 03A. Newbridge Street?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 9 · 500 m · 12 months

Distance
Time
Show all 9

Explore this area on the map →

Homes nearby

Building started

  • 13 Feb 2026 · Builder told the council work was starting (opted out of the finish sign-off) CN0138364OY

Zoning

G5 — Open space and amenity

Land zoned to stay open — parks, playing fields, amenity corridors. Built development is very hard to justify, which also means the view is protected.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

  • NIAH-recorded building · 51
    John Grimes; Wilmer House
  • Recorded monument · 1
    R141449

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.018 Sept 2026, 15:44open
Summary

2560046 is a planning application to Offaly County Council for the development consisting of knocking an existing extension and rebuilding a new, received on 26 Feb 2025; permission was granted with conditions on 4 Sept 2025.