PlanningRegister.ie
Offaly County Council · 2560060

Clondelara, Shannonbridge, Offaly

Approved in 2025. No sign of building yet.

  1. 5 Mar 2025Received
  2. 18 Aug 2025Conditional
  3. 23 Sept 2025Final approval
  4. 22 Sept 2030Approval runs out

Earlier approval here ran out with no sign of building: 17499 (2018)

Applications, appeals and commencement notices for this county. Consultations, zoning and RZLT maps: Dublin, Kildare, Meath and Wicklow only for now.
Status
Approved
Decision
Conditional · 18 Aug 2025
Council
Offaly County Council
Type
PERMISSION
Units
1
Site
3,006 m²

Live near Clondelara?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

1. SITE ACCESS 2. CONSTRUCTION OF A DORMER DWELLING HOUSE 3. CONSTRUCTION OF GARAGE 4. EFFLUENT TREATMENT SYSTEM 5. ALL ASSOCIATED SITE WORKS

Planning details

Reference
2560060
Local authority
Offaly County Council
Status
Granted with conditions · register status “APPLICATION FINALISED”
Received
5 Mar 2025
Observations close
9 Apr 2025 (closed 545 days ago)
Decision due
18 Aug 2025 · decided 18 Aug 2025
Decision
Conditional on 18 Aug 2025
Proposed development
1. SITE ACCESS 2. CONSTRUCTION OF A DORMER DWELLING HOUSE 3. CONSTRUCTION OF GARAGE 4. EFFLUENT TREATMENT SYSTEM 5. ALL ASSOCIATED SITE WORKS
As published by the register.
Site area
3,006 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Nearby 1 · 500 m · 5 years

Explore this area on the map →

Zoning

Not zoned in the current plan.

Protections nearby 250 m

No mapped flood area nearby.

Nothing else protected nearby.

Where this comes from

National planning feed (NPAD), fetched 18 Sept 2026, 15:44.

Source: npad · fetched 18 Sept 2026, 15:44
SourceLicenceFetchedLink
npadCC-BY-4.018 Sept 2026, 15:44open
Summary

2560060 is a planning application to Offaly County Council for 1. site access 2. construction of a dormer dwelling house 3. construction of garage 4., received on 5 Mar 2025; permission was granted with conditions on 18 Aug 2025.