Meera and Tullyleague, Carrick-on-Shannon, Co. Roscommon
Approved in Mar 2026. No sign of building yet.
- 29 Jan 2025Received
- 5 Feb 2026Conditional
- 13 Mar 2026Final approval
- 12 Mar 2036Approval runs out
- Status
- Approved
- Decision
- Conditional · 5 Feb 2026
- Council
- Roscommon County Council
- Type
- PERMISSION
- Site
- 40.36 ha
What’s proposed
Permission for development consisting of a solar farm development comprising of: the installation of photovoltaic panels on ground mounted frames in rows; a 38kV ESB electricity substation compound including a single storey substation building and electrical infrastructure; up to 23 no. single inverter stations (or an alternative string inverter provision); ducting and underground electrical cabling; provision of some new internal access tracks and use of some existing agricultural tracks; storage containers; perimeter fencing; pole mounted CCTV cameras; vehicular access via existing private roads that connect directly to the L50783; construction of 2 no. passing bays along the L50783 and all associated site development and landscaping works. All on a site of approximately 37.97 hectares. The solar farm will have an operational lifespan of 40 years and an estimated export capacity of 30MW approx. of electricity. Planning permission is sought for a duration of 10 years at
Planning details
- Reference
- 2560026
- Local authority
- Roscommon County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 29 Jan 2025
- Decision due
- 5 Feb 2026 · decided 5 Feb 2026
- Decision
- Conditional on 5 Feb 2026
- Site area
- 40.36 ha from the mapped boundary, not the council's figure
Live near Meera and Tullyleague?
Everything else planned on your street, in one report.
Check my streetNearby 3 · 500 m · 5 years
Homes nearby
Zoning
Zoned for waterfront and harbour-related development.
Protections nearby 250 m
- Recorded monument · 7
Where this comes from
National planning feed (NPAD), fetched 28 Oct 2026, 01:34.
Source: National Planning Application Database · fetched 28 Oct 2026, 01:34
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 28 Oct 2026, 01:34 | open |
Summary
2560026 is a planning application to Roscommon County Council for permission for development consisting of a solar farm development comprising of: the, received on 29 Jan 2025; permission was granted with conditions on 5 Feb 2026.