PlanningRegister.ie
Roscommon County Council · 2560446

Pollymount Bellanamullia Scramoge, Treanaceeve and Ballyhubert, County Roscommon

Approved in Aug 2026.

What’s proposed

Permission for development consisting of: • The construction and operation of a wind farm consisting of six wind turbines; • The turbine specification is unconfirmed but will fall within the parameter range outlined by Roscommon County Council and will be one of the following three Options; - Technology Option 1: tip height of 160m, rotor diameter of 136m and hub height of 92m; or - Technology Option 2: tip height of…

Show all

156m, rotor diameter of 133m and hub height of 90m; or - Technology Option 3: tip height of 159m, rotor diameter of 138m and hub height of 90m; • Construction of turbine hardstands (including crane and assembly areas) and turbine foundations; • Construction of approximately 3.9km of new permanent internal site access tracks and the upgrade of 0.5km of existing internal site access tracks; • Construction of a permanent onsite 38kV electrical substation, including one single storey substation building with welfare facilities, Lidar, diesel generator and fuel storage tank, all associated electrical plant and equipment, all associated underground cabling, rainwater harvesting and storage tank, wastewater holding tank, security fencing, gates, signage, and all ancillary structures and works; • Installation of underground electrical and communications cabling connecting the wind turbines to the proposed onsite 38kV electrical substation; • Construction of two temporary site compounds with associated site offices, welfare facilities, car parking, site fencing and lighting; • Erection of a permanent 30m high communications relay tower; • Construction access via six site entrances (SE1 – SE6) to include: - SE1 on the R371, SE2 and SE3 on the L6018, and SE4, SE5 and SE6 on the L60498; - SE1 and SE6 are temporary and will be reinstated following construction. SE1 may be re-established if required for turbine component repair or replacement. SE2 – SE5 will be retained permanently for operational access; • Tree felling to facilitate the construction and operation of the proposed development; • Installation of approximately 5.1km of permanent underground electrical cabling for the grid connection including cabling within the public road corridor, extending from the proposed onsite 38kV electrical Substation at Ballyfeeny to end at the junction of the R371 and the Sliabh Bawn Substation Road in the townland of Tooreen; • All associated site works, including site clearance, landscaping, site drainage…

Cut short by the council feed. Full text ↗

  1. 15 Sept 2025Received
  2. 20 Aug 2026Conditional
  3. 20 Aug 2031Approval runs out

An email when the appeal is decided, and if building then starts.

Planning details

Status
Under appeal
Decision
Conditional · 20 Aug 2026
Reference
2560446
Received
15 Sept 2025
Further information
Requested 23 Dec 2025 · received 17 Jun 2026
Site
49.77 ha

Every application, appeal and deadline within 500 m

Get the full report

Explore this area on the map →

Homes nearby

Appeal

Appeal PL-502020-RN-26 (status unknown), not yet matched.

Protections nearby 250 m

  • Recorded monument · 4
    R163249; R163416
Where this comes from

National planning feed (NPAD), fetched 24 Nov 2026, 23:00.

Source: National Planning Application Database · fetched 24 Nov 2026, 23:00
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.024 Nov 2026, 23:00open
Summary

2560446 is a planning application to Roscommon County Council for permission for development consisting of: • The construction and operation of a wind, received on 15 Sept 2025; permission was granted with conditions on 20 Aug 2026.