Carrowkeel Longfield, Kilmass Grange & Rahara, Co. Roscommon
With the council, no decision yet.
- 17 Apr 2026Received
- 22 May 2026Observations closed
- Status
- With the council, no decision yet
- Decision
- Not yet
- Council
- Roscommon County Council
- Type
- PERMISSION
- Site
- 33.97 ha
Live near Carrowkeel Longfield?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
Permission for a 10 year planning permission for the proposed development of a wind farm on a site area of 27.4 hectares in the townlands of Townlands of Carrowkeel, Longfield, Kilmass, Grange, Rahara, Co. Roscommon. The proposed development for which permission is sought will comprise: • Four (4) wind turbines with an overall blade tip height of 184.55 metres (m) to 185m, a rotor diameter of 149.1m to 163m, a hub height of 103.5m to 110m, and associated foundations, hard-standing and assembly areas; • A permanent 38kV on-site electrical substation within a compound area of 1,034m² to consist of: a control building containing welfare facilities, all associated electrical plant and equipment, perimeter security fencing, entrance gates, underground cabling, a wastewater holding tank, a rainwater harvesting tank, parking, lighting and lightning protection mast 18m in height; and all associated infrastructure and services including CCTV and signage; • A permanent Battery Energy Storage System (BESS) within an area of 1,014m² adjacent to the substation, to consist of 32 Battery units, 4 PCS (Power Conversion System) inverters, 2 PCS MV (Medium Voltage) transformers connected to the HV (High Voltage) substation transformer, and perimeter security fencing; • Upgrade of an existing agricultural entrance from the R362 Regional Road for use as a permanent site entrance by all vehicular traffic during construction and operation; • Upgrade of approximately 700m of existing internal agricultural access tracks, to include passing bays for internal site traffic and all associated drainage; • Approximately 2,400m of new internal permanent access tracks, to include passing bays for internal site traffic and all associated drainage; • Re-use of approximately 17,595m³, of excavated peat for landscaping within the site to a maximum height of 0.5m and subsequent re-vegetation; • A temporary site compound within an area of 4,000m², containing temporary site offices, waste storage areas, parking areas and perimeter security fencing; • A meteorological mast with a height of 36m and associated foundation; • Temporary and permanent drainage and sediment control systems; • Felling of approximately 5.5ha of forestry to facilitate construction and operation of the proposed wind farm; • Biodiversity enhancement measures to include replanting of 2.42ha of trees and 1,240m of hedgerows on-site; • All associated underground electrical and communications cabling
Planning details
- Reference
- 2660172
- Local authority
- Roscommon County Council
- Status
- With the council, no decision yet · register status “FURTHER INFORMATION”
- Received
- 17 Apr 2026
- Observations close
- 22 May 2026 (closed 150 days ago)
- Decision
- Not decided
- Site area
- 33.97 ha from the mapped boundary, not the council's figure
Nearby none · 500 m · 5 years
No other application within 500 m in the last 5 years.
Homes nearby
Protections nearby 250 m
- Recorded monument · 12
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: National Planning Application Database · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database | CC BY 4.0 | 18 Sept 2026, 15:44 | open |
Summary
2660172 is a planning application to Roscommon County Council for permission for a 10 year planning permission for the proposed development of a wind farm, received on 17 Apr 2026; no decision has been recorded yet.