What’s proposed
Permission is sought for Grid System Services Limited, applying for a 10-year permission to develop an Energy Storage System, which will connect to the adjoining ESB Tonroe 110kV Electricity Substation. The proposed development will have a projected life span of 35 years. The development will consist of the construction of 1) enclosed battery energy storage system within a site compound on a total of up to c. 2.33 hectare site, to include: 1 no. single storey 110kV customer substation, control and switch rooms; up to 44 battery blocks on concrete support structures including heating, ventilation and air conditioning unit (HVAC units); up to 11 transformer and inverter units; including access tracks and site entrance along existing roadway; associated electrical cabling and ducting; security gates, 2.6m palisade perimeter security fencing; CCTV system; landscaping works and all other associated ancillary infrastructure at
2660302 is a planning application to Roscommon County Council for permission is sought for Grid System Services Limited, applying for a 10-year permission, received on 22 Jun 2026; no decision has been recorded yet.
Planning details
- Reference
- 2660302
- Local authority
- Roscommon County Council
- Status
- With the council, no decision yet · register status “FURTHER INFORMATION”
- Received
- 22 Jun 2026
- Observations close
- 27 Jul 2026 (closed 56 days ago)
- Decision due
- No due date published
- Decision
- Not decided
- Proposed development
- Permission is sought for Grid System Services Limited, applying for a 10-year permission to develop an Energy Storage System, which will connect to the adjoining ESB Tonroe 110kV Electricity Substation. The proposed development will have a projected life span of 35 years. The development will consist of the construction of 1) enclosed battery energy storage system within a site compound on a total of up to c. 2.33 hectare site, to include: 1 no. single storey 110kV customer substation, control and switch rooms; up to 44 battery blocks on concrete support structures including heating, ventilation and air conditioning unit (HVAC units); up to 11 transformer and inverter units; including access tracks and site entrance along existing roadway; associated electrical cabling and ducting; security gates, 2.6m palisade perimeter security fencing; CCTV system; landscaping works and all other associated ancillary infrastructure atAs published by the register.
- Site area
- 2.05 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 5 applications within 500 m in the last 5 years
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 456909). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/RoscommonCC/AppFileRefDetails/2660302/0.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |