South Dublin County Council · SD21A/0162

Brownsbarn, Citywest Campus, Dublin 24

Approved in May 2022. Built and signed off.

  1. 22 Jun 2021Received
  2. 28 Mar 2022Approved
  3. 12 May 2022Final approval
  4. 24 May 2022Building started
  5. 21 Jun 2023Signed off
Status
Building started
Decision
Approved · 28 Mar 2022
Council
South Dublin County Council
Type
Permission
Site
4.06 ha

Live near Brownsbarn?

Everything else planned on your street, in one report.

Check my street
Council register ↗

What’s proposed

Construction of 2 warehouses with ancillary office and staff facilities and associated development; Unit 1 will have a maximum height of 16.35 metres with a gross floor area of 8,156sq.m including a warehouse area (7,397sq.m), ancillary office areas (362sq.m) and staff facilities (397sq.m); Unit 2 will have a maximum height of 15.35 metres with a gross floor area of 5,990sq.m including a warehouse area (5,031sq.m), ancillary office areas (536sq.m) and staff facilities (423sq.m); vehicular access/egress routes to the subject site via the existing roundabout and access road; alteration to the existing access arrangements to the subject lands to facilitate safe traffic flow to/from the proposed facilities; pedestrian access; 109 car parking spaces; bicycle parking; HGV Parking; HGV yards; level access goods doors; dock levellers; access gates; signage; hard and soft landscaping; lighting; boundary treatments; ESB substation; sprinkler tanks; pump houses; and all associated site development works above and below ground on lands bounded to the south by the N7 Naas Road, to the north and west by the National Distribution Centre and to the east by Brownsbarn Drive and the Royal Garter Stables, a Protected Structure (RPS Ref. 261)

Planning details

Reference
SD21A/0162
Local authority
South Dublin County Council
Status
Commenced · register status “Decision Following A.I.”
Received
22 Jun 2021
Observations close
5 Apr 2022 (closed 1661 days ago)
Decision due
28 Mar 2022 · decided 28 Mar 2022
Decision
Grant permission on 28 Mar 2022
Site area
4.06 ha from the mapped boundary, not the council's figure

Nearby 22 · 500 m · 5 years

Show all 22

Explore this area on the map →

Homes nearby

Development land nearby

From Buildable, our sister site for development land in Dublin.

See all development land near here →

Building started

  • 4 Aug 2022 · Builder told the council work was starting (seven-day notice) SN0007517SD
  • 24 May 2022 · Builder told the council work was starting (seven-day notice) SN0007254SD
  • 24 May 2022 · Builder told the council work was starting (seven-day notice) SN0007253SD

Zoning

C2.1 — Economic development and employment

Zoned for employment uses. Housing is not the intended use here.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • EPA-licensed facility · 1
    Independent Newspapers (Ireland) Limited
  • NIAH-recorded building · 1
    Brown's Barn

Where this comes from

National planning feed (NPAD), fetched 14 Oct 2026, 01:45.

Source: National Planning Application Database · fetched 14 Oct 2026, 01:45
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.014 Oct 2026, 01:45open
Summary

SD21A/0162 is a planning application to South Dublin County Council for construction of 2 warehouses with ancillary office and staff facilities and associated, received on 22 Jun 2021; permission was granted on 28 Mar 2022.