PlanningRegister.ie
South Dublin County Council · SD21A/0167

Profile Park, Baldonnel, Dublin 22

Approved in Aug 2022. Building started in 2023.

  1. 25 Jun 2021Received
  2. 19 Jul 2022Approved
  3. 30 Aug 2022Final approval
  4. 4 Apr 2023Building started
Status
Building startedi
Decision
Approved · 19 Jul 2022
Council
South Dublin County Council
Type
Permission
Site
6,687 m²

What’s proposed

In plain English

Construction of a gas fired power plant in Profile Park

The applicant wants to build a gas fired power plant with an electrical output of up to 125MW. This includes several buildings, storage tanks, and an exhaust stack.

  • Includes an exhaust stack with a height of 31.8m
  • Features an engine hall building 18.9m high
  • Adds 2 new access points onto the existing private road network
  • Includes 12 parking spaces and landscaping
Written by AI from the council’s description

An AI model rewrote the council’s description below in everyday words on 9 Oct 2026. It was told to use only that text, and every number it wrote was checked against it. It says nothing about whether the application will be approved. The council’s wording and planning file are the record.

The council’s description

Construction of a gas fired power plant with an electrical output of up to 125MW with associated balance of plant, equipment and buildings including; an Engine Hall building with a height of 18.9m, comprising 6 gas engines and ancillary infrastructure; an Electrical Annex Building with a height of 18.7m; a Workshop building with a height of 5. 1m; a Tank Farm building with a height of 5.68m; a Security hut with a height of 3.27m; an Exhaust Stack with a height of 31.8m; a Gas AGI including a kiosk with height of 3.3m; Radiator Coolers with a height of 8.46m; 2 electrical transformers with a height of 4.98m; Tanks including 2 x Diesel Oil Storage Tanks (volume of 2500m3 combined); SCR Urea Tank (26m3); Lube Oil Storage Tank (26m3); Lube Oil Maintenance Tank (26m3); Pilot Oil Tank (26m3); Fire Water Storage Tank (1000m3); Effluent Collecting Tank (26m3); Underground Surface Water Attenuation Tank (490m3); 2 new access onto the existing private road network with Profile Park; 12 parking spaces, footpaths, landscaping; fencing and all other associated site development plant and equipment and other works including surface water and foul wastewater drainage. An EIAR was submitted with this application

Planning details

Reference
SD21A/0167
Local authority
South Dublin County Council
Status
Commenced · register status “Decision Following A.I.”
Received
25 Jun 2021
Decision due
19 Jul 2022 · decided 19 Jul 2022
Decision
Grant permission on 19 Jul 2022
Site area
6,687 m² from the mapped boundary, not the council's figure

Live near Profile Park?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 3 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 1 Feb 2024 · Builder told the council work was starting CN0109355SD
  • 30 Jun 2023 · Builder told the council work was starting (seven-day notice) SN0008644SD
  • 30 Jun 2023 · Builder told the council work was starting (seven-day notice) SN0008645SD
  • 4 Apr 2023 · Builder told the council work was starting (seven-day notice) SN0008309SD

Zoning

C2.1 — Economic development and employment

Zoned for employment uses. Housing is not the intended use here.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • EPA-licensed facility · 4
    P1189; P1196

Where this comes from

National planning feed (NPAD), fetched 14 Oct 2026, 01:45.

Source: National Planning Application Database · fetched 14 Oct 2026, 01:45
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.014 Oct 2026, 01:45open
Summary

SD21A/0167 is a planning application to South Dublin County Council for construction of a gas fired power plant with an electrical output of up to 125MW with, received on 25 Jun 2021; permission was granted on 19 Jul 2022.