South Dublin County Council · SD21A/0167

Profile Park, Baldonnel, Dublin 22

  1. 25 May 2022Received
  2. 19 Jul 2022Grant permission
  3. 30 Aug 2022Final grant
  4. 1 Feb 2024Commenced
Applications only for this county. Appeals, zoning, RZLT and consultations: Dún Laoghaire-Rathdown and Fingal only for now.
Status
Commenced
Decision
Grant permission · 19 Jul 2022
Council
South Dublin County Council
Type
Permission
Site
6,687 m²

What’s proposed

Construction of a gas fired power plant with an electrical output of up to 125MW with associated balance of plant, equipment and buildings including; an Engine Hall building with a height of 18.9m, comprising 6 gas engines and ancillary infrastructure; an Electrical Annex Building with a height of 18.7m; a Workshop building with a height of 5. 1m; a Tank Farm building with a height of 5.68m; a Security hut with a height of 3.27m; an Exhaust Stack with a height of 31.8m; a Gas AGI including a kiosk with height of 3.3m; Radiator Coolers with a height of 8.46m; 2 electrical transformers with a height of 4.98m; Tanks including 2 x Diesel Oil Storage Tanks (volume of 2500m3 combined); SCR Urea Tank (26m3); Lube Oil Storage Tank (26m3); Lube Oil Maintenance Tank (26m3); Pilot Oil Tank (26m3); Fire Water Storage Tank (1000m3); Effluent Collecting Tank (26m3); Underground Surface Water Attenuation Tank (490m3); 2 new access onto the existing private road network with Profile Park; 12 parking spaces, footpaths, landscaping; fencing and all other associated site development plant and equipment and other works including surface water and foul wastewater drainage. An EIAR was submitted with this application

SD21A/0167 is a planning application to South Dublin County Council for construction of a gas fired power plant with an electrical output of up to 125MW with, received on 25 May 2022; permission was granted on 19 Jul 2022.

Planning details

Reference
SD21A/0167
Local authority
South Dublin County Council
Status
Commenced · register status “Decision Following A.I.
Received
25 May 2022
Observations close
29 Jun 2022 (closed 1539 days ago)
Decision due
19 Jul 2022 · decided 19 Jul 2022
Decision
Grant permission on 19 Jul 2022
Proposed development
Construction of a gas fired power plant with an electrical output of up to 125MW with associated balance of plant, equipment and buildings including; an Engine Hall building with a height of 18.9m, comprising 6 gas engines and ancillary infrastructure; an Electrical Annex Building with a height of 18.7m; a Workshop building with a height of 5. 1m; a Tank Farm building with a height of 5.68m; a Security hut with a height of 3.27m; an Exhaust Stack with a height of 31.8m; a Gas AGI including a kiosk with height of 3.3m; Radiator Coolers with a height of 8.46m; 2 electrical transformers with a height of 4.98m; Tanks including 2 x Diesel Oil Storage Tanks (volume of 2500m3 combined); SCR Urea Tank (26m3); Lube Oil Storage Tank (26m3); Lube Oil Maintenance Tank (26m3); Pilot Oil Tank (26m3); Fire Water Storage Tank (1000m3); Effluent Collecting Tank (26m3); Underground Surface Water Attenuation Tank (490m3); 2 new access onto the existing private road network with Profile Park; 12 parking spaces, footpaths, landscaping; fencing and all other associated site development plant and equipment and other works including surface water and foul wastewater drainage. An EIAR was submitted with this application
As published by the register.
Site area
6,687 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name council register

Around this site this application first, then everything within 500 m

Explore from hereFree report
Click a dot to open its row.
Loading planning applications…
Free · during launch · limited time

Full planning report for 53.31515, -6.44239

Zoning, appeals, sold prices, flood and heritage constraints — everything for this area in one PDF.

No account, no payment. Not a statutory planning search.

Appeal

Not appealed.

Commencement

  • Commencement notice CN0109355SD
    1 Feb 2024Site partially bounded by Profile Park road on the east, north and west., Profile Park, South Dublinmatched by ref_exact
  • Seven day notice SN0008644SD
    30 Jun 2023Site partially bounded by Profile Park road on the east, north and west., Profile Park, South Dublinmatched by ref_exact
  • Seven day notice SN0008645SD
    30 Jun 2023Site partially bounded by Profile Park road on the east, north and west., Profile Park, South Dublinmatched by ref_exact
  • Seven day notice SN0008309SD
    4 Apr 2023Site partially bounded by Profile Park road on the east, north and west., Profile Park, South Dublinmatched by ref_exact

Zoning at the site

C2.1 — Economic development and employment

EE: To provide for enterprise and employment related uses

Zoned for employment uses. Housing is not the intended use here.

Designations within 250 m

OPW flood extent nearby — flag only (licence); floodinfo.ie.

  • EPA-licensed facility · 4
    P1189; P1196; P1203
  • Radon risk area · 1
    About 1 in 20 homes in this area is likely to have high radon levels

Provenance

Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 116113). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/southdublin/application-details/60998.

Source: npad · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
npadCC-BY-4.011 Sept 2026, 18:51open