PlanningRegister.ie
South Dublin County Council · SD23B/0516

43 Wilkin's Court, Dublin 12, D12 Y15N

Approved in Mar 2024. Building started in 2024.

  1. 14 Dec 2023Received
  2. 8 Feb 2024Approved
  3. 21 Mar 2024Final approval
  4. 7 May 2024Building started
Status
Building startedi
Decision
Approved · 8 Feb 2024
Council
South Dublin County Council
Type
Permission
Site
175 m²

What’s proposed

Conversion of existing attic space comprising of modification of existing roof structure, new access stairs, A-style roof dormer and 2 no. roof windows to the front and flat roof dormer to the rear

Planning details

Reference
SD23B/0516
Local authority
South Dublin County Council
Status
Commenced · register status “Final Grant”
Received
14 Dec 2023
Decision due
16 Feb 2024 · decided 8 Feb 2024
Decision
Grant permission on 8 Feb 2024
Site area
175 m² from the mapped boundary, not the council's figure

Live near 43 Wilkin's Court?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 10 · 500 m · 12 months

Distance
Time
Show all 10

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 7 May 2024 · Builder told the council small works were starting CN0114770SD

Zoning

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

  • NIAH-recorded building · 1
    Catholic Church of the Holy Spirit

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

SD23B/0516 is a planning application to South Dublin County Council for conversion of existing attic space comprising of modification of existing roof, received on 14 Dec 2023; permission was granted on 8 Feb 2024.