SD24A/0012 is a planning application for permission at Junction of Naas Road/Long Mile Road, Walkinstown, Dublin 12, received by South Dublin County Council on 27 Aug 2024 and first seen by Planning Register on 11 Sept 2026. The application describes: Part demolition of the existing forecourt building (31.44 sq.m), the removal of the existing car wash, compound, storage shed, totem signs, one fuel pump island (resulting in 3 No. pump islands remaining), and associated reduction in size of canopy at Maxol Long Mile Road Junction, Naas Rd/Long Mile Road, Walkinstown, Dublin 12, 012 TDW3, and the demolition of existing building (180 sq.m) removal of portacabin (61 sq m) and the part removal of boundary treatments at Beechlawn Motors, The Huntsman Service Station, Naas Road, Dublin 12, 012 DC62 to incorporate it into the Maxol site consisting of construction of: 215 sq.m extension of the existing forecourt building resulting in a single storey forecourt building of 555 sq.m total gross floor area (comprising a retail unit (100 sq.m net area, including a 11 sq.m ancillary off licence), 3 No. restaurant/cafe areas (which will include the sale of hot and cold food for consumption on and off the premises) one of which will include a drive-thru facility, seating area, back of house areas and circulation spaces) with revised facades and screened roof plant; substation/ switch room (23.5 sq.m); car wash plant room (7.5 sq.m); solid fuel store (8 sq.m); external compound; and an EV Charging Hub (consisting of 6EV charging spaces; a canopy; ancillary plant; substation (11 sq.m)) revisions to the overall site layout (including the provision of 30 No. car parking spaces (separate to the EV Hub spaces); motorbike and bicycle parking spaces; alterations to vehicular circulation (including amendment of existing vehicular access point at the Beechlawn Motors site to provide entry only, and provision of a drive thru lane); new car wash facility, offset fills and vents; and alterations to external lighting); changes to levels; hard and soft landscaping, including revised boundary treatments; associated site servicing (water supply, foul and surface water drainage including surface water attenuation measures); all other associated site development works above and below ground. The development will also consist of 35 No. signs: 2 No. replacement 7m high double sided internally illuminated totem signs; 1 No.4.8m high double sided internally illuminated totem sign associated with the EV Hub; 11 No. attached to the forecourt building (7 No. of which are illuminated); 9 No. free- standing signs (4 No. of which are illuminated); 12 No. attached to other structures. The development will also consist of: a temporary structure (72 sq.m) to accommodate a shop (net retail area 36 sq.m), storage, ancillary support facilities; and the temporary siting of the proposed solid fuel store (8 sq.m) during the construction phase. The council granted permission on 23 Sept 2024. The five-week observation window closed on 1 Oct 2024. A commencement notice (SN0012908SD) was lodged on 15 Aug 2025, so works have started on site. The site is zoned M1 — metro / rail economic corridor under the South Dublin County Council development plan. Within 500 m there are 22 other decided applications in the last five years and 2 appeals.
Proposal
Part demolition of the existing forecourt building (31.44 sq.m), the removal of the existing car wash, compound, storage shed, totem signs, one fuel pump island (resulting in 3 No. pump islands remaining), and associated reduction in size of canopy at Maxol Long Mile Road Junction, Naas Rd/Long Mile Road, Walkinstown, Dublin 12, 012 TDW3, and the demolition of existing building (180 sq.m) removal of portacabin (61 sq m) and the part removal of boundary treatments at Beechlawn Motors, The Huntsman Service Station, Naas Road, Dublin 12, 012 DC62 to incorporate it into the Maxol site consisting of construction of: 215 sq.m extension of the existing forecourt building resulting in a single storey forecourt building of 555 sq.m total gross floor area (comprising a retail unit (100 sq.m net area, including a 11 sq.m ancillary off licence), 3 No. restaurant/cafe areas (which will include the sale of hot and cold food for consumption on and off the premises) one of which will include a drive-thru facility, seating area, back of house areas and circulation spaces) with revised facades and screened roof plant; substation/ switch room (23.5 sq.m); car wash plant room (7.5 sq.m); solid fuel store (8 sq.m); external compound; and an EV Charging Hub (consisting of 6EV charging spaces; a canopy; ancillary plant; substation (11 sq.m)) revisions to the overall site layout (including the provision of 30 No. car parking spaces (separate to the EV Hub spaces); motorbike and bicycle parking spaces; alterations to vehicular circulation (including amendment of existing vehicular access point at the Beechlawn Motors site to provide entry only, and provision of a drive thru lane); new car wash facility, offset fills and vents; and alterations to external lighting); changes to levels; hard and soft landscaping, including revised boundary treatments; associated site servicing (water supply, foul and surface water drainage including surface water attenuation measures); all other associated site development works above and below ground. The development will also consist of 35 No. signs: 2 No. replacement 7m high double sided internally illuminated totem signs; 1 No.4.8m high double sided internally illuminated totem sign associated with the EV Hub; 11 No. attached to the forecourt building (7 No. of which are illuminated); 9 No. free- standing signs (4 No. of which are illuminated); 12 No. attached to other structures. The development will also consist of: a temporary structure (72 sq.m) to accommodate a shop (net retail area 36 sq.m), storage, ancillary support facilities; and the temporary siting of the proposed solid fuel store (8 sq.m) during the construction phase.
- Status
- Final Grant
- Decision
- Grant permission on 23 Sept 2024
- Final grant
- 8 Nov 2024
- Permission expires
- 7 Nov 2029
- Floor area
- 265 m²
- Site (from polygon)
- 5,022 m²
- Location precision
- site (coords_polygon)
Timeline
- 13 Mar 2024Further information requested
- 20 Jun 2024Further information received
- 27 Aug 2024New applicationObservation window closed 1 Oct 2024
- 23 Sept 2024DecisionAppeal window closed 21 Oct 2024

Full planning report for 53.32388, -6.35059
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
- Seven day notice SN0012908SD
Zoning at the site
REGEN: To facilitate enterprise and/or residential led regeneration
A high-density mixed-use employment corridor tied to a rail or metro line. Expect the tallest buildings in the area here.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- EPA-licensed facility · 3
- Radon risk area · 3
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 117839). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/southdublin/application-details/65463.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |