SD24A/0145W is a planning application for permission at JFK Enterprise Centre, Bluebell, Dublin 12, D12 F229., received by South Dublin County Council on 9 Oct 2024 and first seen by Planning Register on 11 Sept 2026. The application describes: 1) The erection of a 2.3m high black palisade fence to the north, east and part of the west boundaries 2) Remove the foyer and rebuild a new one: a sloping roof with a height not exceeding 3380mm, a width of 3680mm, and a depth of 2630mm 3) Within the company courtyard, approximately 700 square meters of asphalt pavement is laid around the main building 4) Erecting company signage on the main building overall size 0.9m x 18.75m 5) Add 19 No. street lights within the company forecourt 6) Install two electric gates 7) Add metal lines above the roof of the main building 8) Repainting exterior wall paint 9) Replace all doors and windows of the main building, the outer frame color of doors and windows is gun grey 10) On the southeast side of the main building, establish a 4700mm wide and 3100mm high billboard. The council granted permission on 5 Nov 2024. The five-week observation window closed on 13 Nov 2024. A commencement notice (CN0124708SD) was lodged on 17 Jan 2025, so works have started on site. The site is zoned M1 — metro / rail economic corridor under the South Dublin County Council development plan. Within 500 m there are 28 other decided applications in the last five years.
Proposal
1) The erection of a 2.3m high black palisade fence to the north, east and part of the west boundaries 2) Remove the foyer and rebuild a new one: a sloping roof with a height not exceeding 3380mm, a width of 3680mm, and a depth of 2630mm 3) Within the company courtyard, approximately 700 square meters of asphalt pavement is laid around the main building 4) Erecting company signage on the main building overall size 0.9m x 18.75m 5) Add 19 No. street lights within the company forecourt 6) Install two electric gates 7) Add metal lines above the roof of the main building 8) Repainting exterior wall paint 9) Replace all doors and windows of the main building, the outer frame color of doors and windows is gun grey 10) On the southeast side of the main building, establish a 4700mm wide and 3100mm high billboard.
- Status
- Final Grant
- Decision
- Grant permission on 5 Nov 2024
- Final grant
- 19 Dec 2024
- Permission expires
- 18 Dec 2029
- Floor area
- 10 m²
- Site (from polygon)
- 3,625 m²
- Location precision
- site (coords_polygon)
Timeline
- 6 Aug 2024Further information requested
- 1 Oct 2024Further information received
- 9 Oct 2024New applicationObservation window closed 13 Nov 2024
- 5 Nov 2024DecisionAppeal window closed 3 Dec 2024

Full planning report for 53.32685, -6.35226
One document, every dataset, each section with its source and fetch time. Print it or download it as a PDF. It informs a planning search; it is not a statutory search.
1 Where this is — preview
1 Deadlines still open
Appeal
Not appealed.
Commencement
- Commencement notice CN0124708SD
Zoning at the site
REGEN: To facilitate enterprise and/or residential led regeneration
A high-density mixed-use employment corridor tied to a rail or metro line. Expect the tallest buildings in the area here.
Designations within 250 m
OPW flood extent nearby — flag only (licence); floodinfo.ie.
- EPA-licensed facility · 6
- Radon risk area · 3
Provenance
Register row from the national planning applications feed (NPAD), fetched 11 Sept 2026, 18:51 (store id 113840). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: https://planning.agileapplications.ie/southdublin/application-details/66333.
Source: npad · fetched 11 Sept 2026, 18:51
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 11 Sept 2026, 18:51 | open |